Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $2,878,000 for a total estimated cost of these projects being $6,383,799.38
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $2,878,000. The total estimated cost of these projects is $6,383,799.38.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
2nd Aldermanic District
W. Fond du Lac Ave. and N. 52nd St. Intersection (ST211110151) File Number 100216: Intersection modifications. (Nonassessable Reconstruction Paving Fund -- $40,000). The total estimated cost for this project including the requested amount is $47,000. This project is anticipated to be completed during the 2011 construction season.
4th Aldermanic District
E. State St. - N. Prospect Ave. to N. Edison St. (ST30684015) (2204-01-90) File Number 090761:
City Share Non-Assessable Fund Paving
ST320110000
Fund 0333
$10,000
Estimated Total: $10,000.00
Previously authorized for Traffic Control Improvement (File Number 090890): $276,793.86
Current estimated cost of total project including this resolution: $2,076,693.58
Original estimated cost of project (File Number 950972 ): $604.200.00
This project is anticipated to be completed during the 2011 construction season.
6th Aldermanic District
N. Humboldt Ave. - N. Riverboat Rd. to N. Commerce St. (WT410110781) File N...
Click here for full text