powered help
header-left header-center header-right
File #: 101544    Version: 0
Type: Resolution Status: Passed
File created: 4/12/2011 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 5/3/2011
Effective date:    
Title: Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,715,000 for a total estimated cost of these projects being $3,928,000.
Sponsors: THE CHAIR
Indexes: SANITARY SEWERS, SEWER IMPROVEMENTS, SEWERS
Attachments: 1. Hearing Notice List
Number
101544
Version
ORIGINAL
Reference
100960
Sponsor
THE CHAIR
Title
Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,715,000 for a total estimated cost of these projects being $3,928,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $3,715,000. The total estimated cost of these projects is $3,928,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

1st Aldermanic District

Area bounded by W. Hampton Ave., W. Villard Ave., N. Green Bay Ave., and N. 21st St. (#4) (SM494100106) File Number 100960: Sanitary sewer lining. (Infiltration/Inflow Reduction Fund -- $535,000). The total estimated cost for this project including the requested amount is $550,000. This project is anticipated to be completed during the 2011 construction season.

2nd and 5th Aldermanic Districts

Area bounded by W. Capitol Dr., W. Congress St., N. 68th St., and N. 76th St. (#5) (SM494100109) File Number 100960: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $682,000). The total estimated cost for this project including the requested amount is $697,000. This project is anticipated to be completed during the 2011 construction season.

3rd Aldermanic District

E. Clarke St. - 135 feet m/l east of N. Dousman St. to N. Gordon Pl. (SM495100236) File Number 101095: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $35,000). The total estimate...

Click here for full text