File #: 100215    Version:
Type: Resolution Status: Passed
File created: 6/15/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/7/2010
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,029,400 for a total estimated cost of $3,174,400.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Official Notice Number 8, 3. Official Notice 8 Committee Actions, 4. Email from Department of Public Works, 5. Speed Study, 6. Hearing Notice List, 7. Notice Published on 7-23-10
Number
100215
Version
SUBSTITUTE 1
Reference
081586
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,029,400 for a total estimated cost of $3,174,400.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $3,029,400. The total estimated cost of these projects is $3,174,400.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

4th Aldermanic District

N. 26th St. - W. McKinley Ave. to W. Vliet St. (ST211100157): Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $2,900; Nonassessable Reconstruction Paving Fund -- $8,000). The total estimated cost for this project including the requested amount is $10,900. This project is anticipated to be completed during the 2010 construction season.

9th Aldermanic District

W. Calumet Rd. - N. 51st Blvd. to N. 60th St. (ST21100156) File Number 081586: Asphalt pavement with rural cross-section. Replace driveways as necessary. (Assessable Reconstruction Paving Fund -- $1,200; Nonassessable Reconstruction Paving Fund -- $225,000). The total estimated cost for this project including the requested amount is $250,000. This project is anticipated to be completed during the 2010-2011 construction season.

W. County Line Rd. - N. 91st St./Swan Rd. to N...