Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $771,000 for a total estimated cost of these projects being $3,600,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
221442
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $771,000 for a total estimated cost of these projects being $3,600,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $771,000 with the total cost estimated to be $3,600,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st and 4th Aldermanic Districts

2023 N. 27th St. and W. Highland Blvd. (SM499230003) Bioretention Maintenance (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost of this project is $50,000. This project is anticipated to be completed during the 2023 construction season.

7th and 15th Aldermanic Districts

2023 N. Sherman Blvd. (SM499230004) Bioretention Maintenance (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost of this project is $50,000. This project is anticipated to be completed during the 2023 construction season.

10th Aldermanic District

2023 Maintenance of Areas Under the Wisconsin Ave. Viaduct (SM499230005) (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost of this project is $8,000. This project is anticipated to be completed during the 2023 construction season.

14th Aldermanic District

S. Illinois Ave. - 255’ +/- North of E. Holt Ave. to E...