File #: 221442    Version:
Type: Resolution Status: Passed
File created: 1/17/2023 In control: COMMON COUNCIL
On agenda: Final action: 2/7/2023
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $771,000 for a total estimated cost of these projects being $3,600,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

221442

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $771,000 for a total estimated cost of these projects being $3,600,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $771,000 with the total cost estimated to be $3,600,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

1st and 4th Aldermanic Districts

 

2023 N. 27th St. and W. Highland Blvd. (SM499230003) Bioretention Maintenance (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost of this project is $50,000. This project is anticipated to be completed during the 2023 construction season.

 

7th and 15th Aldermanic Districts

 

2023 N. Sherman Blvd. (SM499230004) Bioretention Maintenance (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost of this project is $50,000. This project is anticipated to be completed during the 2023 construction season.

 

10th Aldermanic District

 

2023 Maintenance of Areas Under the Wisconsin Ave. Viaduct (SM499230005) (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost of this project is $8,000. This project is anticipated to be completed during the 2023 construction season.

 

14th Aldermanic District

 

S. Illinois Ave. - 255’ +/- North of E. Holt Ave. to E. Morgan Ave. (SM495220062) Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $272,000. This project is anticipated to be completed during the 2023 construction season.

 

E. Malvern Pl. - S. Kinnickinnic Ave. to S. Pennsylvania Ave. (SM495220063) Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $140,000. This project is anticipated to be completed during the 2023 construction season.

 

S. Pennsylvania Ave. - 45’ +/- South of E. Ohio Ave. to E. Holt Ave. (SM495220061) Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2023 construction season.

 

City Wide

 

2023 Indirect Account. (SM495230001) (Nonassessable Sewer Maintenance Relay Fund -- $400,000). The total estimated cost of this project including the requested amount is $400,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Northside (SM499230001) Bioretention Maintenance (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost of this project is $290,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Paving Coordination. (SM495230002) (Nonassessable Sewer Maintenance Relay Fund -- $75,000). The total estimated cost of this project including the requested amount is $75,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Sanitary Manhole Inspections. (SM494230001) (Infiltration/Inflow Reduction Fund-- $10,000). The total estimated cost of this project including the requested amount is $200,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Sanitary Manhole Rehabilitation. (SM494230002) (Infiltration/Inflow Reduction Fund-- $15,000). The total estimated cost of this project including the requested amount is $300,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Sewer Exam Requests. (SM495230003) (Nonassessable Sewer Maintenance Relay Fund -- $100,000). The total estimated cost of this project including the requested amount is $100,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Sewer Repairs. (SM495230006) (Nonassessable Sewer Maintenance Relay Fund -- $50,000). The total estimated cost of this project including the requested amount is $50,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Sewer Structure Inspections. (SM495230004) (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost of this project including the requested amount is $40,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Sewer Survey Requests. (SM495230005) (Nonassessable Sewer Maintenance Relay Fund -- $50,000). The total estimated cost of this project including the requested amount is $50,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Sewer Work Prior to Paving. (SM495230500) (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost of this project including the requested amount is $1,250,000. This project is anticipated to be completed during the 2023 construction season.

 

2023 Southside (SM499230002) Bioretention Maintenance (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost of this project is $135,000. This project is anticipated to be completed during the 2023 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 