powered help
header-left header-center header-right
File #: 091015    Version: 0
Type: Resolution Status: Passed
File created: 12/1/2009 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 12/22/2009
Effective date:    
Title: Resolution authorizing the construction of street lighting improvements on various local streets and bridges as part of the Mitchell Interchange Reconstruction, with a total estimated cost of $227,440.40 of which 100% is State funded.
Sponsors: THE CHAIR
Indexes: EXPRESSWAYS, STREET LIGHTING, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Cover Letter, 2. Fiscal Note, 3. Contract, 4. Comptroller's Certification, 5. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
1/6/20100 MAYOR SIGNED   Action details Meeting details Not available
12/22/20090 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
12/9/20090 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual present: Clark Wantoch, Dept. of Public Works, Infrastructure Services
Pass5:0 Action details Meeting details Not available
12/4/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
12/1/20090 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
091015
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the construction of street lighting improvements on various local streets and bridges as part of the Mitchell Interchange Reconstruction, with a total estimated cost of $227,440.40 of which 100% is State funded.
Analysis
This resolution authorizes the Commissioner of Public Works to install interim street lighting facilities, to install permanent street lighting facilities and remove interim street lighting facilities on West Layton Avenue from South 20th Street to South 13th Street, South 20th Street from West Layton Avenue to West Van Norman, West Whitaker Avenue from South 13th Street to South 15th Street, South 16th Street from West Vogel Avenue to a point north West Holmes Avenue, and under deck lighting at the overpasses at West Edgerton Avenue, West Bolivar Avenue, and West Ramsey Avenue and adjoining streets in conjunction with Mitchell Interchange reconstruction. Funding for the construction of the street lighting improvements is to be provided entirely by the Wisconsin Department of Transportation as part of the interchange project, total estimated cost of $227,440.40 of which 100% is State funded.
Body
Whereas, The Wisconsin Department of Transportation is reconstructing the Mitchell Interchange of IH 94, USH 41, IH 43, and IH 894 under the State Highway Improvement Program; and

Whereas, The Interchange reconstruction project provides cost participation for City of Milwaukee street lighting system improvements required due to this construction; and

Whereas The Council has previously passed Common Council File number 090541 on September 22, 2009, for the installation of transformer enclosures as part of this project; and

Whereas, Additional interim and permanent lighting facilities will be installed and interim facilities removed on West Layton Avenue from South 20th Street to South 13th Street, South 20th Street from West Layton Avenue to West Van No...

Click here for full text