powered help
header-left header-center header-right
File #: 180760    Version:
Type: Resolution Status: Passed
File created: 9/5/2018 In control: COMMON COUNCIL
On agenda: Final action: 9/25/2018
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,245,000 for a total estimated cost of these projects being $1,961,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
180760
Version
Substitute 1
Reference
180295
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,245,000 for a total estimated cost of these projects being $1,961,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $1,245,000. The total estimated cost of these projects is $1,961,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

1st Aldermanic District

N. 27th St.-W. Capitol Dr. to W. Roosevelt Dr. (SM499180008) File Number 180760: Bioretention Maintainence Contract. (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $5,000 additional funds.) The total estimated cost for this project including the requested amount is $26,000. This project is anticipated to be completed during the 2018 construction season.

6th Aldermanic District

Humboldt Blvd. (SM499180118) Bluff stabilization (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $30,000. The total requested amount for this project is $30,000. This project is anticipated to be completed during the 2018 construction season.

N. Port Washington Rd. - W. Hampton Ave. to 150’ north of W. Hampton Ave. (WT410180015) File Number 180295: Hydrant alteration. (Nonassessable Water Fund Budget Line 6410 -- $20,000, Additional Funds). The total estimated cost for this project including the request...

Click here for full text