File #: 151746    Version:
Type: Resolution Status: Passed
File created: 3/29/2016 In control: COMMON COUNCIL
On agenda: Final action: 4/15/2016
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $690,000 for a total estimated cost of these projects being $19,153,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/18/20161 MAYOR SIGNED   Action details Meeting details Not available
4/15/20161 COMMON COUNCIL ADOPTEDPass13:0 Action details Meeting details Video Video
4/8/20160 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute A
Pass3:0 Action details Meeting details Video Video
4/8/20161 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski, Department of Public Works
Pass3:0 Action details Meeting details Not available
3/29/20160 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
151746
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $690,000 for a total estimated cost of these projects being $19,153,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $690,000 with the total cost estimated to be $19,153,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

2nd Aldermanic District

N. 76th St. - 110 feet north of W. Leon Terr. To 140 feet north of W. Sheridan Ave. (SM495160031): Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $184,000. This project is anticipated to be completed during the 2016 construction season.

4th Aldermanic District

E. Chicago St. - N. Water St. to N. Milwaukee St. (SM495160030): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $25,000). The total estimated cost for this project including the requested amount is $1,000,000. This project is anticipated to be completed during the 2016 construction season.

W. Highland Ave. - Old World Third St. to N. 4th St. (WT410170623): Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $5,000; Nonassessable Water Fund Budget Line 6410 -- $10,000). The total estimated cost for this project including the requested amount is $110,000. This project is anticipated to be completed during the 2017 construction seaso...