Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $560,000 for a total estimated cost of these projects being $1,301,300.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $560,000. The total estimated cost of these projects is $1,301,300.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
2nd Aldermanic District
W. Custer Ave. - N. 60th St. to N. 64th St. (ST211150212) File Number 150848: Install traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $15,000). The total estimated cost for this project including the requested amount is $16,000. This project is anticipated to be completed during the 2015 construction season.
4th Aldermanic District
E. Clybourn St. - N. Milwaukee St. to N. Van Buren St. (WT410140620) File Number 150617: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $150,000, Additional Funds). The total estimated cost for this project including the requested amount is $515,000. This project is anticipated to be completed during the 2016 construction season.
E. Clybourn St. - N. Van Buren St. to N. Harbor Dr. (WT410150704) File Number 150617: Relaying water main and water main extension. (Nonassessable Water Fund Budget Line 6410 -- $250,000, Additional Funds). The total estimated cost for this project including the reque...