Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $560,000 for a total estimated cost of these projects being $1,301,300.
Sponsors: THE CHAIR
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
11/11/20151 MAYOR SIGNED   Action details Meeting details Not available
11/2/20151 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Video Video
10/21/20151 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute A Mary Dziewiontkoski - Department of Public Works
Pass5:0 Action details Meeting details Video Video
10/21/20151 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - Department of Public Works
Pass5:0 Action details Meeting details Not available
10/13/20150 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

150849

Version

Substitute 1

Reference

150848

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $560,000 for a total estimated cost of these projects being $1,301,300.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $560,000.  The total estimated cost of these projects is $1,301,300.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

2nd Aldermanic District

 

W. Custer Ave. - N. 60th St. to N. 64th St. (ST211150212) File Number 150848:  Install traffic calming devices.  (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $16,000.  This project is anticipated to be completed during the 2015 construction season.

 

4th Aldermanic District

 

E. Clybourn St. - N. Milwaukee St. to N. Van Buren St. (WT410140620) File Number 150617:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $150,000, Additional Funds).  The total estimated cost for this project including the requested amount is $515,000.  This project is anticipated to be completed during the 2016 construction season.

 

E. Clybourn St. - N. Van Buren St. to N. Harbor Dr. (WT410150704) File Number 150617:  Relaying water main and water main extension.  (Nonassessable Water Fund Budget Line 6410 -- $250,000, Additional Funds).  The total estimated cost for this project including the requested amount is $600,000.  This project is anticipated to be completed during the 2016 construction season.

 

13th Aldermanic District

 

S. 13th St. - W. Rawson Ave. to W. College Ave. (Portions in the City of Oak Creek) (SM495150085) File Number 090761 (SM495090110) (SW170070115):  Install new storm sewer in the County-State paving project (ST320040501) (2505-06-70) area.  City Share Non-assessable Sewer Fund (SM495150085 -- $60,000, Additional Funds).  The total estimated cost for this project including the requested amount is $80,300.  This project was completed during the 2010 construction season.

 

14th Aldermanic District

 

E. Rusk Ave. - S. Kinnickinnic Ave. to a point west (ST214150104) File Number 150848:  Concrete alley replacement, replace curb and gutter, walk, and driveway as necessary.  (Developer Paving Fund -- $31,000).  The total estimated cost for this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2015 construction season.

 

15th Aldermanic District

 

N. 17th St. - W. North Ave. to W. Lloyd St. (SM499150109) File Number 150848:  Stormwater improvements (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $54,000).  The total estimated cost for this project including the requested amount is $55,000.  This project is anticipated to be completed during the 2015 construction season.

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Nfr 3