File #: 080625    Version: 0
Type: Resolution Status: Passed
File created: 9/2/2008 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 9/16/2008
Effective date:    
Title: Resolution authorizing the Commissioner of Public Works and Comptroller to execute a Project Agreement with the Department of Transportation for the installation of six traffic control signals and to fund preliminary engineering for the project in the 3rd, 7th, and 11th Aldermanic Districts with a total estimated cost of $40,000, with an estimated grantor share of $32,000, and an estimated City share of $8,000.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, TRAFFIC CONTROL SIGNALS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Cover Letter, 2. Fiscal Note, 3. Agreement, 4. Comptroller's Certificate, 5. 080625 Hearing notice list
Number
080625
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the Commissioner of Public Works and Comptroller to execute a Project Agreement with the Department of Transportation for the installation of six traffic control signals and to fund preliminary engineering for the project in the 3rd, 7th, and 11th Aldermanic Districts with a total estimated cost of $40,000, with an estimated grantor share of $32,000, and an estimated City share of $8,000.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to execute a Project Agreement with the Wisconsin Department of Transportation for the programming, design, and construction of six traffic control signals and to fund preliminary engineering for the project in the 3rd, 7th, and 11th Aldermanic Districts. The total estimated cost of the project is $390,000, with a grantor share of $312,000, and a City share of $78,000. The total estimated preliminary engineering cost for the project is $40,000, with a grantor share of $32,000 and a City share of $8,000. Approval of construction costs will be in a future resolution.
Body
Whereas, The submittal of a Congestion Mitigation/Air Quality (CMAQ) grant application to the Wisconsin Department of Transportation (WISDOT) was approved by the Common Council under File Number 061545; and

Whereas, Preliminary approval has been requested and received from WISDOT, along with a Project Agreement to be executed by the City of Milwaukee, for the programming, design, and construction of six traffic control signals that meet Federal warrants for installation under the 2008 CMAQ Program to replace existing all-way stop control; and

Whereas, The intersections of West Howard Avenue and South 43rd Street, West Howard Avenue and South 51st Street, West Howard Avenue and South 68th Street, West Howard Avenue and South 84th Street, East Kane Place and North H...