Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City cost estimated to be $1,049,000 for a total estimated cost of these projects being $30,873,414.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter.pdf, 2. Fiscal Note
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
6/29/20062 MAYOR SIGNED   Action details Meeting details Not available
6/20/20062 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
6/7/20061 PUBLIC WORKS COMMITTEE AMENDED

Minutes note: Ald. Witkowski moved to amend the following project listed under the 8th Aldermanic District, W. Canal St. by changing the "total estimated cost for this project including the requested amount from $3,650,000 to 29,883,414. Prevailed.
Pass5:0 Action details Meeting details Not available
6/7/20062 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
6/6/20060 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
6/2/20060 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
6/2/20061 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
5/31/20060 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
060136
Version
SUBSTITUTE 2
Reference

Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City cost estimated to be $1,049,000 for a total estimated cost of these projects being $30,873,414.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $1,049,000. The total estimated cost of these projects is $30,873,414.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

5th Aldermanic District

N. 88th St. - W. Burleigh St. to W. Concordia Ave. (SM495050072) File Number 050718: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $140,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the 2006 construction season.

7th Aldermanic District

W. Burleigh St. at N. 44th St. (SM495050080) File Number 050718: Storm sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $25,000). The total estimated cost for this project including the requested amount is $30,000. This project is anticipated to be completed during the 2006 construction season.

W. Burleigh St. - N. 47th St. to N. 49th St. (SM495050081) File Number 050718: Relay sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $207,000). The total estimated cost for this project including the requested amount is $220,000. This project is anticipated to be completed during the 2006 constructi...