Number
060136
Version
SUBSTITUTE 2
Reference
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City cost estimated to be $1,049,000 for a total estimated cost of these projects being $30,873,414.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $1,049,000. The total estimated cost of these projects is $30,873,414.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
5th Aldermanic District
N. 88th St. - W. Burleigh St. to W. Concordia Ave. (SM495050072) File Number 050718: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $140,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the 2006 construction season.
7th Aldermanic District
W. Burleigh St. at N. 44th St. (SM495050080) File Number 050718: Storm sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $25,000). The total estimated cost for this project including the requested amount is $30,000. This project is anticipated to be completed during the 2006 construction season.
W. Burleigh St. - N. 47th St. to N. 49th St. (SM495050081) File Number 050718: Relay sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $207,000). The total estimated cost for this project including the requested amount is $220,000. This project is anticipated to be completed during the 2006 constructi...
Click here for full text