Title: Resolution authorizing the Commissioner of Public Works to execute utility agreement with the State of Wisconsin Department of Transportation for work on City of Milwaukee Sanitary Sewer facilities in conjunction with the Zoo Interchange’s Core Phase 1 contract work.
Sponsors: THE CHAIR
Indexes: INTERGOVERNMENTAL AGREEMENTS, SANITARY SEWERS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Agreement Construction Cost Summary, 2. Agreement, 3. Summary of Soft Costs, 4. Comptrollers Certificate, 5. Hearing Notice List
Number
130934
Version
Original
Reference
Sponsor
The Chair
Title
Resolution authorizing the Commissioner of Public Works to execute utility agreement with the State of Wisconsin Department of Transportation for work on City of Milwaukee Sanitary Sewer facilities in conjunction with the Zoo Interchange’s Core Phase 1 contract work.
Analysis
This resolution approves the entitled Agreement for Payment for the Relocation or Replacement of Municipal Utility Facilities Located on Public Held Land Required by Freeway Construction for City of Milwaukee Sanitary Sewer facilities, and authorizes the Commissioner of Public Works to execute the agreement on behalf of the City of Milwaukee.

This agreement relates to utility work on City of Milwaukee Sanitary Sewer facilities necessitated by the rehabilitation of the Zoo Interchange Core Phase 1 contract being undertaken by the Wisconsin Department of Transportation in 2014. This agreement provides generally for the City to be reimbursed from the State 90 percent of the City costs for all work on City of Milwaukee Sanitary Sewer facilities necessitated by the freeway rehabilitation project in accord with Wisconsin State Statute 84.295(4m).

This resolution also authorizes the Commissioner of Public Works to prepare and review plans and estimates for the Zoo Interchange utility work as necessary to accomplish the project. This resolution also authorizes the Comptroller to establish accounts as necessary to track the work and to submit invoices to the State of Wisconsin for work undertaken on this project as approved by the Commissioner of Public Works, for a total amount of $30,000 with a City share of $3,000.

Body
Whereas, The State of Wisconsin Department of Transportation has scheduled the reconstruction of the Zoo Interchange in the City of Milwaukee, Milwaukee County; and

Whereas, There will be work required on City of Milwaukee Sanitary Sewer facilities as a result of the design and construction associat...