powered help
header-left header-center header-right
File #: R_12923    Version: 0
Type: Housing Authority Resolution Status: Passed
File created: 12/8/2017 In control: HOUSING AUTHORITY
On agenda: 12/14/2017 Final action: 12/14/2017
Effective date:    
Title: Resolution approving an award of contract to Rams Contracting, Ltd. (Lannon, WI) for Phase Four Building Demolition, Hazardous Materials Abatement and Site Clearance of Westlawn Phase 2 in an amount of $1,371,000.00 (Official Notice No. 57827)
Sponsors: THE CHAIR
Attachments: 1. IFB Tab & Attachment 57827 Westlawn Phase Four Demolition Rams Contracting.pdf

Number

R_12923

 

Version

Original

 

Reference

 

Sponsor

The Chair

 

Title

Resolution approving an award of contract to Rams Contracting, Ltd. (Lannon, WI) for Phase Four Building Demolition, Hazardous Materials Abatement and Site Clearance of Westlawn Phase 2 in an amount of $1,371,000.00 (Official Notice No. 57827)

 

Analysis

 

Body

WHEREAS, the Housing Authority of the City of Milwaukee (Authority) solicited sealed bids by Official Notice Number 57827 during the period November 3, 2017 through November 30, 2017 for Hazardous Materials Abatement, Building Demolition, and Site Clearance (Phase 4) at Westlawn Gardens Phase 2; and

 

WHEREAS, three sealed bids were received by the deadline of 2:00 PM (CST) on November 30, 2017; and

 

WHEREAS, the sealed bids were received and publicly opened on November 30, 2017, during which bidding procedure was conducted in compliance with the requirements of local, state, and federal regulations; and

 

WHEREAS, Rams Contracting Ltd., a qualified and competent bidder, submitted the lowest responsive and responsible bid in the amount of $1,371,000.00, therefore, be it

 

RESOLVED, by the Commissioners of the Authority that they hereby authorize and approve accepting the bid of and entering into a contract with Rams Contracting Ltd. for Hazardous Materials Abatement, Building Demolition, and Site Clearance (Phase 4) at Westlawn Gardens Phase 2; and, be it

 

FURTHER RESOLVED, that funds for these services will come from the Capital Fund Program 2018 Grant; and, be it

 

FURTHER RESOLVED, that the proper officers of the Authority be and hereby are authorized and directed to properly execute said contract for and on behalf of the Authority; and, be it

 

FURTHER RESOLVED, that if any extensions of the time of performance are needed the Chairman and Secretary-Executive Director may approve such request without any further action of the Authority; and, be it

 

FURTHER RESOLVED, that all of above is contingent upon receiving the approval of the U.S. Department of Housing and Urban Development, if required; and, be it

 

FURTHER RESOLVED, that all acts previously performed relative to this matter by the Commissioners and the Secretary Executive Director of the Authority be and hereby are approved, ratified, and confirmed in all respects.

 

Requestor

 

Drafter

M&D, November 21, 2017