Number
110354
Version
Substitute 2
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $146,800 for a total estimated cost of these projects being $1,341,800.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $146,800 with the total cost estimated to be $1,341,800.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
2nd Aldermanic District
W. Stark St. - N. 64th St. to N. 68th St. (SM495110534): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $2,000). The total estimated cost for this project is $2,000. This project is anticipated to be completed during the 2011-2012 construction season.
3rd Aldermanic District
Alley between N. Cramer St., E. Hampshire St., E. Hartford Ave., and N. Oakland Ave. (SM495110538): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $1,500). The total estimated cost for this project is $1,500. This project is anticipated to be completed during the 2011-2012 construction season.
4th Aldermanic District
W. McKinley Blvd. - N. 27th St. to N. 35th St. (SM495110539): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $70,000). The total estimated cost for this project is $70,000. This project is anticipated to be completed during the 2011-2012 construction season.
5th Aldermanic District
W. Bobolink Ave. - W. Appleton Ave. to N. Lovers Ln. Rd. (SM495110535): Sewer wor...
Click here for full text