powered help
header-left header-center header-right
File #: 110162    Version:
Type: Resolution Status: Passed
File created: 5/24/2011 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 6/14/2011
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,025,100 for a total estimated cost of $1,118,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, STREET IMPROVEMENTS
Attachments: 1. Official Notice #6 Committee Actions, 2. Official Notice #6, 3. Cover Letter, 4. Hearing Notice List, 5. Notice Published 6-30-11
Number
110162
Version
SUBSTITUTE 1
Reference
101437
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,025,100 for a total estimated cost of $1,118,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,025,100. The total estimated cost of these projects is $1,118,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

3rd Aldermanic District

Alley between E. Bradford Ave., N. Downer Ave., N. Stowell Ave., and E. Webster Pl. (ST212110103) File Number 101437: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $32,700; Nonassessable Alley Paving Fund -- $40,000). The total estimated cost for this project including the requested amount is $63,000. This project is anticipated to be completed during the 2011-2012 construction season.

5th Aldermanic District

N. 78th St. - N. 79th St. to W. Hope Ave. (ST211060105) File Number 100596: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (9.0-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $7,400; Nonassessable Reconstruction Paving Fu...

Click here for full text