Number
110028
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,472,000 for a total estimated cost of these projects being $3,008,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $1,472,000 with the total cost estimated to be $3,008,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
3rd Aldermanic District
N. Marietta Ave. - E. Locust St. to E. Kenwood Blvd. (SM495110525): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $45,000). The total estimated cost for this project is $45,000. This project is anticipated to be completed during the 2011 construction season.
N. Weil St. - E. Concordia Ave. to 125 feet m/l south of E. Townsend Ave. (SM495110046): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $95,000. This project is anticipated to be completed during the 2011 construction season.
3rd and 6th Aldermanic Districts
E. Auer Ave. - N. Holton St. to N. Bremen St. (SM495110045): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $427,000. This project is anticipated to be completed during the 2011 construction season.
5th Aldermanic District
N. 81st St. - W. Fiebrantz Ave. to W. Hope Ave. (SM495110521): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $53,000). The total estimated cost for this project is $53,000. This project is anticipated to be completed during the 2011 construction season.
N. 119th St. - W. Hampton Ave. to a point north of W. Hampton Ave. (SM495110523): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $25,000). The total estimated cost for this project is $25,000. This project is anticipated to be completed during the 2011 construction season.
N. 122nd St. - W. Florist Ave. to W. Lynx Ave. (SM495110524): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost for this project is $20,000. This project is anticipated to be completed during the 2011 construction season.
6th Aldermanic District
N. Humboldt Ave. - N. Riverboat Rd. to N. Commerce St. (WT410110781): Water main relay. (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000). The total estimated cost for this project including the requested amount is $300,000. This project is anticipated to be completed during the 2012 construction season.
7th Aldermanic District
N. 36th St. - W. Hope Ave. to 275 feet m/l north of W. Hope Ave. (SM495110048): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $1,000). The total estimated cost for this project including the requested amount is $57,000. This project is anticipated to be completed during the 2011 construction season.
N. 42nd St. - W. Burleigh St. to W. Townsend St. (SM495110520): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $40,000). The total estimated cost for this project is $40,000. This project is anticipated to be completed during the 2011 construction season.
N. 49th St. - W. Keefe Ave. to W. Vienna St. (SM495110047): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $282,000. This project is anticipated to be completed during the 2011 construction season.
7th and 15th Aldermanic Districts
N. 19th St. - W. Center St. to W. Locust St. (SM495110040): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $461,000. This project is anticipated to be completed during the 2011 construction season.
8th Aldermanic District
W. Becher St. - S. 24th St. to S. Layton Blvd. (SM495110533): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $30,000). The total estimated cost for this project is $30,000. This project is anticipated to be completed during the 2011 construction season.
W. Lapham St. - S. Layton Blvd. to S. 29th St. (SM495110532): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost for this project is $20,000. This project is anticipated to be completed during the 2011 construction season.
W. Mitchell St. - S. Layton Blvd. to S. 32nd St. (SM495110527): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $33,000). The total estimated cost for this project is $33,000. This project is anticipated to be completed during the 2011 construction season.
9th Aldermanic District
W. Calumet Rd. - N. 51st St. to N. 60th St. (SM495110522): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $5,000). The total estimated cost for this project is $5,000. This project is anticipated to be completed during the 2011 construction season.
10th Aldermanic District
N. 44th St. - W. Blue Mound Rd. to W. Wells St. (SM495110515): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $5,000). The total estimated cost for this project is $5,000. This project is anticipated to be completed during the 2011 construction season.
S. 60th St. - W. Dickinson St. to W. Main St. (SM495110528): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $17,000). The total estimated cost for this project is $17,000. This project is anticipated to be completed during the 2011 construction season.
11th Aldermanic District
W. Crawford Ave. - W. Tripoli Ave. to S. 73rd St. (SM495110517): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $25,000). The total estimated cost for this project is $25,000. This project is anticipated to be completed during the 2011 construction season.
S. Sunset Dr. - W. Wedgewood Dr. to W. Morgan Ave. (SM495110529): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $2,000). The total estimated cost for this project is $2,000. This project is anticipated to be completed during the 2011 construction season.
S. 38th St. - W. Morgan Ave. to W. Holt Ave. (SM495110531): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $5,000). The total estimated cost for this project is $5,000. This project is anticipated to be completed during the 2011 construction season.
S. 63rd St. - W. Eden Pl. to W. Morgan Ave. (SM495110514): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $28,000). The total estimated cost for this project is $28,000. This project is anticipated to be completed during the 2011 construction season.
12th Aldermanic District
W. Maple St. - S. 6th St. to S. 13th St. (SM495110526): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $63,000). The total estimated cost for this project is $63,000. This project is anticipated to be completed during the 2011 construction season.
13th Aldermanic District
W. Euclid Ave. - S. 16th St. to S. 20th St. (SM495110530): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $25,000). The total estimated cost for this project is $25,000. This project is anticipated to be completed during the 2011 construction season.
S. 20th St. - South City Limits to W. College Ave. (SM495110516): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $50,000). The total estimated cost for this project is $50,000. This project is anticipated to be completed during the 2011 construction season.
14th Aldermanic District
E. Lincoln Ave. - S. Kinnickinnic Ave. to S. 1st St. (SM495110519): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $65,000). The total estimated cost for this project is $65,000. This project is anticipated to be completed during the 2011 construction season.
E. Potter Ave. - S. Logan Ave. to S. Kinnickinnic Ave. (SM495110518): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $30,000). The total estimated cost for this project is $30,000. This project is anticipated to be completed during the 2011 construction season.
City Wide
Paving Coordination - Administration (SM495110015): The total estimated cost for this project is $300,000. This project is anticipated to be completed during the 2011 construction season.
2011 City Paving Projects - Administration (SM495110049): The total estimated cost for this project is $500,000. This project is anticipated to be completed during the 2011 construction season.
;and, be it
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Npr 12
05/06/2011