Title: Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,140,000 for a total estimated cost of these projects being $4,034,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SEWER IMPROVEMENTS, SEWERS, WATER MAINS
Attachments: 1. Hearing Notice List

Number

101172

Version

ORIGINAL

Sponsor

THE CHAIR

Title

Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,140,000 for a total estimated cost of these projects being $4,034,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $1,140,000 with the total cost estimated to be $4,034,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

3rd Aldermanic District

 

N. Cambridge Ave. - E. Brady St. to N. Oakland Ave. (WT410110025):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. Oakland Ave. - E. Royall Pl. to E. Windsor Pl. (WT410110026):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $15,000; Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $475,000.  This project is anticipated to be completed during the 2011 construction season.

 

4th Aldermanic District

 

N. Jackson St. - E. Clybourn St. to a point north of E. Clybourn St. (ST211110173):  Median revision.  (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $25,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 25th St. - W. St. Paul Ave. to W. Clybourn St. (WT410091015):  Relaying water main and lining.  (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $27,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 33rd St. - W. Vliet St. to W. Cherry St. (SM495110009):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $93,000.  This project is anticipated to be completed during the 2011 construction season.

 

5th Aldermanic District

 

W. Appleton Ave. (south side) - W. Glendale Ave. to W. Hampton Ave. (SM495110008):  Sanitary sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $112,000.  This project is anticipated to be completed during the 2011 construction season.

 

W. Capitol Dr. - W. Grantosa Dr. to Grantosa Creek (SM495110010):  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $22,000.  This project is anticipated to be completed during the 2011 construction season.

 

6th Aldermanic District

 

W. Hadley St. - N. 1st St. to N. Dr. Martin Luther King Jr. Dr. (SM495110004):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $308,000.  This project is anticipated to be completed during the 2011 construction season.

 

7th and 10th Aldermanic Districts

 

N. 50th St. - N. Gengler Cr. to W. Concordia Ave. (SM495110003):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $299,000.  This project is anticipated to be completed during the 2011 construction season.

 

8th Aldermanic District

 

S. 37th St. - W. Branting Ln. to W. Burnham St. (SM495110002):  Relaying sanitary and storm sewers.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $456,000.  This project is anticipated to be completed during the 2011 construction season.

 

12th Aldermanic District

 

W. Scott St. - 170 feet m/l east of S. 7th St. to S. 6th St. (SM495110006):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $64,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 6th St. - W. Greenfield Ave. to W. Scott St. (SM495110005):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2011 construction season.

 

13th Aldermanic District

 

S. 6th St. Green Street Project - W. Grange Ave. to W. Howard Ave. (SM493100103):  (Nonassessable TSS Removal Fund -- $25,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2011 construction season.

 

City Wide

 

Catch Basin and Manhole Adjustments Prior to Paving (SM495110011):  (Nonassessable Sewer Maintenance Relay Fund -- $1,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2011 construction season.

 

2011 Indirect Account/Engineering Studies throughout the City of Milwaukee (SM495110001):  (Nonassessable Sewer Maintenance Relay Fund -- $800,000).  The total estimated cost for this project is $800,000.  This project is anticipated to be completed during the 2011 construction season.

 

Various Aldermanic Districts

 

Bridge Indirect and Administration (BR100110101):  (City Share Non-assessable Structure Fund -- $125,000).  The total estimated cost for this project is $125,000.  This project is anticipated to be completed during the 2011 construction season.

 

; and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Npr 7