powered help
header-left header-center header-right
File #: 100960    Version: 0
Type: Resolution Status: Passed
File created: 11/23/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 12/21/2010
Effective date:    
Title: Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $235,000 for a total estimated cost of these projects being $26,965,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SANITARY SEWERS, SEWER IMPROVEMENTS, SEWERS
Attachments: 1. Hearing Notice List

Number

100960

Version

ORIGINAL

Sponsor

THE CHAIR

Title

Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $235,000 for a total estimated cost of these projects being $26,965,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $235,000 with the total cost estimated to be $26,965,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

1st Aldermanic District

 

Area bounded by W. Hampton Ave., W. Villard Ave., N. Green Bay Ave., and N. 21st St. (#4) (SM494100106):  Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $15,000).  The total estimated cost for this project including the requested amount is $2,930,000.  This project is anticipated to be completed during the 2011 construction season.

 

2nd and 5th Aldermanic Districts

 

Area bounded by W. Capitol Dr., W. Congress St., N. 68th St., and N. 76th St. (#5) (SM494100109):  Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $15,000).  The total estimated cost for this project including the requested amount is $3,384,000.  This project is anticipated to be completed during the 2011 construction season.

 

4th Aldermanic District

 

N. Jefferson St. - E. Buffalo St. to E. St. Paul Ave. (SM495100122):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $113,000.  This project is anticipated to be completed during the 2011 construction season.

 

5th Aldermanic District

 

Area bounded by W. Center St., W. Burleigh St., N. 82nd St., and N. 92nd St. (#3) (SM494100107):  Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $15,000).  The total estimated cost for this project including the requested amount is $4,300,000.  This project is anticipated to be completed during the 2011 construction season.

 

6th Aldermanic District

 

W. Keefe Ave. - N. 18th St. to N. 19th St. (SM495100149):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $2,000,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 6th St. - W. Capitol Dr. to W. Fiebrantz Ave. (SM495100151):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2011 construction season.

 

7th Aldermanic District

 

Area bounded by W. Capitol Dr., W. Concordia Ave., N. 35th St., and W. Fond du Lac Ave. (#6) (SM494100108):  Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $15,000).  The total estimated cost for this project including the requested amount is $5,384,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. Sherman Blvd. - W. Fiebrantz Ave. to W. Capitol Dr. (SM495100150):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $300,000.  This project is anticipated to be completed during the 2011 construction season.

 

9th Aldermanic District

 

(N/S) Sewer Easement between N. Delta Pl., N. Edgeworth Dr., N. Port Ave., and W. Bradley Rd. (SM495100117):  New storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $1,400,000.  This project is anticipated to be completed during the 2011 construction season.

 

10th Aldermanic District

 

W. Fairview Ave. - N./S. 63rd St. to N./S. 68th St. (SM495100148):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $600,000.  This project is anticipated to be completed during the 2011 construction season.

 

11th Aldermanic District

 

Area bounded by Greenfield City Limits and W. Morgan Ave., S. 34th St., and S. 31st St. (SM495100211):  Sanitary sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $126,000.  This project is anticipated to be completed during the 2011 construction season.

 

12th Aldermanic District

 

S. 4th St. - W. Orchard St. to W. Lapham Blvd. (SM495100216):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $115,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 13th St. - W. Hayes Ave. to W. Harrison Ave. (SM495100089):  Separation relay.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $2,000,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 15th Pl. - W. Lincoln Ave. to W. Windlake Ave. (SM495100102):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $113,000.  This project is anticipated to be completed during the 2011 construction season.

 

13th Aldermanic District

 

Area bounded by W. Layton Ave., W. Edgerton Ave., S. 20th St., and S. 27th St. (#18) (SM494100110):  Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $15,000).  The total estimated cost for this project including the requested amount is $3,800,000.  This project is anticipated to be completed during the 2011 construction season.

 

15th Aldermanic District

 

N. 26th St. at W. Lisbon Ave. (SM495100005):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2011 construction season.

 

Various Aldermanic Districts

 

Asphalt resurfacing of various streets by contract (ST211110168):  This project is anticipated to be completed during the 2011 construction season.

 

Sealcoating of various streets by contract (ST211110169):  This project is anticipated to be completed during the 2011 construction season.

 

Crackfilling of various streets by contract (ST211110170):  This project is anticipated to be completed during the 2011 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Npr 5