File #: 241061    Version:
Type: Resolution Status: Passed
File created: 11/6/2024 In control: COMMON COUNCIL
On agenda: Final action: 11/26/2024
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $75,000 for a total estimated cost of these projects being $514,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
241061
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $75,000 for a total estimated cost of these projects being $514,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $75,000 with the total cost estimated to be $514,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st Aldermanic District

W. Fairmount Ave. - N. Sherman Blvd. to N. 44th St. (WT410250659) Relaying water main. (Nonassessable Water Fund Budget Line 5010--$1,000; Nonassessable Water Fund Budget Line 6410--$14,000). The total estimated cost for this project including the requested amount is $140,000. This project is anticipated is anticipated to be completed during the 2026 construction season.

2nd Aldermanic District

N. 76th St. - W. Bobolink Pl. to 120’ North of W. Florist Ave. (WT410250601) File number 231828: Relaying water main. (Nonassessable Water Fund Budget Line 6410--$20,000 additional funding). The total estimated cost for this project including the requested amount is $160,000. This project is anticipated to be completed during the 2025 construction season.

7th Aldermanic District

N. 47th St. - W. Center St. to W. Hadley St. (SM495240034) Relaying storm sewer. (Nonassessable Sewer Maintenance Relay fund--$15,000) The total estimated cost of this project including the requested amount is $164,000. The project is anticipated to be completed during the ...