File #: 100328    Version: 0
Type: Resolution Status: Passed
File created: 7/7/2010 In control: FINANCE & PERSONNEL COMMITTEE
On agenda: Final action: 7/27/2010
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute a revised project agreement titled “State/Municipal Agreement” for a highway improvement project with Wisconsin Department of Transportation for the reconstruction of West Capitol Drive from North 60th Street to Mayfair Road with State/Federal Aid.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, HIGHWAYS, STATE GRANTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Cover Letter, 2. Agreement, 3. Comptroller's Certification, 4. Fiscal Note, 5. PW Hearing Notice List, 6. F & P Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
8/5/20100 MAYOR SIGNED   Action details Meeting details Not available
7/27/20100 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
7/21/20100 FINANCE & PERSONNEL COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individuals present: Mark Nicolini, DOA-Budget Office Ald. Murphy asks that the engineers contact himself, Ald. Bauman and Ald. Bohl about improving the physical appearance along the corridor.
Pass5:0 Action details Meeting details Not available
7/16/20100 FINANCE & PERSONNEL COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/14/20100 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION AND ASSIGNED

Minutes note: Individual present: Clark Wantoch, Department of Public Works-Infrastructure Services
Pass5:0 Action details Meeting details Not available
7/12/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/7/20100 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

100328

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution directing the Commissioner of Public Works to execute a revised project agreement titled “State/Municipal Agreement” for a highway improvement project with Wisconsin Department of Transportation for the reconstruction of West Capitol Drive from North 60th Street to Mayfair Road with State/Federal Aid. 

Analysis

This resolution directs the Commissioner of Public Works to execute a revised project agreement with the Wisconsin Department of Transportation (WisDOT) for the programming and reconstruction of West Capitol Drive (STH 190) from North 60th Street to West Mayfair Road with State/Federal Aid under the State Trunk Highway program.  The revised agreement splits preliminary engineering into two phases.  Phase I is from North 60th Street to North 84th Street to be constructed in 2012 and Phase II is from North 84th Street to Mayfair Road to be constructed in 2013.The estimated total cost of the project is $22,450,500, of which the City’s share is $1,692,250 and the grantor’s share is $20,758,250.  The estimated preliminary engineering cost is $3,009,000 of which the City’s share is $752,250 and the grantor’s share is $2,256,750.

Body

Whereas, The Common Council of the City of Milwaukee adopted resolution file numbers 041289 and 061548 on February 11, 2005 and April 25, 2007, respectively, directing the Commissioner of Public Works to execute a State/Municipal Agreement with Wisconsin Department of Transportation (WisDOT) for the programming and construction of West Capitol Drive from North 60th Street to West Mayfair Road; and

 

Whereas, The Department of Public Works (DPW) requested and the WisDOT agreed to break preliminary engineering of the roadway project into two phases.  Phase I going from North 60th Street to North 84th Street scheduled for construction in 2012 and Phase II from North 84th Street to West Mayfair Road scheduled for construction in 2013; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is hereby authorized to execute the revised project agreement for the preliminary engineering of West Capitol Drive from North 60th Street to West Mayfair Road with State/Federal Aid under the WisDOT State Trunk Highway Program in two phases, a copy of which is attached to Common Council File 100328 and is incorporated by reference as though set forth in full; and, be it

 

Further Resolved, That the Commissioner of Public Works is hereby authorized and directed to undertake or engage a consultant to undertake preliminary engineering for the improvement of the aforementioned projects and to reimburse the WisDOT for preliminary engineering costs they incur for the improvement; and, be it

 

Further Resolved, That the Commissioner of Public Works is hereby authorized and directed to enter into an agreement with the WisDOT pertaining to the cost participation for the installation and/or modification of traffic control facilities in conjunction with the improvements of the aforementioned projects; and, be it

 

Further Resolved, That the Commissioner of Public Works is hereby authorized and directed to install the traffic control facilities necessary in conjunction with the aforementioned project, following the execution of the traffic control agreement, the cost of which will be included in future resolutions; and, be it

 

Further Resolved, That the Commissioner of Pubic Works is hereby authorized and directed to negotiate and enter into cost-sharing agreements with the City of Wauwatosa for the West Capitol Drive Street project; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project/Grant Chartfield Values for preliminary engineering for the projects (Expenditures) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

Infrastructure Services Division:

State I.D. 2025-11-00

West Capitol Drive (STH 190)

Mayfair Road to North 60th Street

 

City Non-Assessable Paving

ST320070501

Fund 0333

($720,000)

 

Grantor Reimbursable Cash Paving

ST320070501

Fund 0333

($1,800,000)

 

Grantor Non-Reimbursable Paving

($360,000)

 

Infrastructure Services Division

State I.D. 2025-11-00

West Capitol Drive (STH 190)

North 84th Street to North 60th Street

 

City of Milwaukee Non-Assessable Paving

ST320100000

Fund 0333

$282,000

 

Grantor Reimbursable Cash Paving

SP032100100

Fund 0306

$705,000

 

Grantor Non-Reimbursable Paving

$141,000

 

Construction is scheduled for 2012

 

Previously authorized for preliminary engineering: $2,880,000

Current estimated cost of total project including this resolution: $22,450,500

Original estimated cost of the total project (Resolution #061548): $19,065,000

 

Infrastructure Services Division

State I.D. 2025-11-01

West Capitol Drive (STH 190)

Mayfair Road to North 84th Street

 

City of Milwaukee Non-Assessable Paving

ST320100000

Fund 0333

$470,250

 

Grantor Reimbursable Cash Paving

SP032100100

Fund 0306

$1,175,625

 

Grantor Non-Reimbursable Paving

$235,125

 

Construction is scheduled for 2013.

 

Previously authorized for preliminary engineering: $0

Current estimated cost of total project including this resolution: $22,450,500

Original estimated cost of the total project (Resolution #061548): $19,065,000

 

; and, be it

 

Further Resolved, That the City Engineer is hereby authorized and directed to approve and make periodic payments to the WisDOT upon receipt of invoices for the City of Milwaukee’s share of costs on the projects.

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

LCG:amh

June 29, 2010

Reso W Captl (STH 190) M-Fai Rd - N 60 062910.rtf