Number
100131
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the City Comptroller to transfer funds to various State and Federal Aid project subaccounts for the estimated remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering and construction costs totaling $741,681.00, with a City share is $741,681.00.
Analysis
This resolution authorizes the City Comptroller to transfer funds to the previously established subaccounts for the remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering and construction costs in the amount of $741,681.00. The City of Milwaukee’s share is $741,681.00.
Body
Whereas, The Common Council has previously adopted resolutions authorizing the City Comptroller to transfer funds to various State and Federal Aid project subaccounts for preliminary engineering and construction; and
Whereas, Additional planning and review during the design state and additional work during the construction stage have resulted in increased costs charged against the projects; and
Whereas, Additional funds are, therefore, necessary for the estimated remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering and construction costs for the projects; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the City Comptroller is hereby authorized and directed to transfer funds to the project grant chartfields as follows:
Project Grant Value
2555-06-00
ST320081201
West Burleigh Street
Intersection with West Roosevelt Drive and North 60th Street
City Share Non-Assessable Paving
ST320100000
0333
$40,000
Previously Authorized for Engineering - $49,964.76
Current Estimated Cost of the Total Project including this Resolution - $344,440.76
Original Estimated Cost of the Total Project (Resolution File No. 071689): - $276,076.00
Project Grant Value
2984-25-02/03
ST320041110
Canal Street-South 25th Street to South 6th Street/Hank Aaron State Trail
City Share Non-Assessable Paving
ST320100000
0333
$220,159.29
City Share Assessable Paving
ST320100000
0330
($220,159.29)
Project Grant Value
2984-03-70
ST520090210
North Teutonia Avenue-West Mill Road to West Silver Spring Drive (ARRA)
City Share Non-Assessable Paving
ST320100000
0333
$139,127.00
Previously Authorized for Construction - $30,000.00
Current Estimated Cost of the Total Project including this Resolution - $753,217.00
Original Estimated Cost of the Total Project (Resolution File No. 090538): - $560,000.00
Project Grant Value
2984-03-70
ST520090310
North Teutonia Avenue-West Good Hope Road to Mill Road (ARRA)
City Share Non-Assessable Paving
ST320100000
0333
$139,127.00
Previously Authorized for Construction - $30,000.00
Current Estimated Cost of the Total Project including this Resolution - $812,127.00
Original Estimated Cost of the Total Project (Resolution File No. 090538): - $615,000.00
Project Grant Value
2984-03-70
ST520090510
West Locust Street-West Hopkins Street to North 8th Street (ARRA)
City Share Non-Assessable Paving
ST320100000
0333
$96,783.00
Previously Authorized for Construction - $30,000.00
Current Estimated Cost of the Total Project including this Resolution - $583,783.00
Original Estimated Cost of the Total Project (Resolution File No. 090538): - $445,000.00
Project Grant Value
2984-03-70
ST520090410
North Martin Luther King Drive-West McKinley Avenue to West Burleigh Street (ARRA)
City Share Non-Assessable Paving
ST320100000
0333
$229,861.00
Previously Authorized for Construction - $30,000.00
Current Estimated Cost of the Total Project including this Resolution - $1,764,861.00
Original Estimated Cost of the Total Project (Resolution File No. 090538): - $1,465,000.00
Summary of projects in this resolution:
City Share Non-Assessable Paving - $961,840.29
City Share Assessable Paving - ($220,159.29)
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
MK:ns
April 27, 2010
6/28/10 Account # Correction dkf