Number
100024
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution directing the Commissioner of Public Works to execute a revised project agreement titled “State/Municipal Agreement” for a highway improvement project with Wisconsin Department of Transportation for the reconstruction of West Capitol Drive from North 60th Street to Mayfair Road (STH 100) with State/Federal Aid.
Analysis
This resolution directs the Commissioner of Public Works to execute a revised project agreement with the Wisconsin Department of Transportation (WisDOT) for the programming and reconstruction of West Capitol Drive (STH 190) from North 60th Street to West Mayfair Road (STH 100) with State/Federal Aid under the State Trunk Highway program. The revised agreement splits roadway construction into two phases. Phase I is from North 60th Street to North 84th Street to be constructed in 2012 and Phase II is from North 84th Street to Mayfair Road (STH 100) to be constructed in 2013. The estimated total cost of the project is $22,339,725, of which the City’s share is $1,664,556 and the grantor’s share is $20,675,169. The estimated preliminary engineering cost is $3,018,225 of which the City’s share is $724,556 and the grantor’s share is $2,293,669.
Body
Whereas, The Common Council of the City of Milwaukee adopted resolution file number 041289 on February 11, 2005 directing the Commissioner of Public Works to execute a State/Municipal Agreement with Wisconsin Department of Transportation (WisDOT) for the programming and construction of West Capitol Drive from North 60th Street to West Mayfair Road (STH 100); and
Whereas, The Department of Public Works (DPW) requested and the WisDOT agreed to break construction of the roadway project into two phases. Phase I going from North 60th Street to North 84th Street scheduled for construction in 2012 and Phase II from North 84th Street to West Mayfair Road (STH 100) scheduled for construction in 2013; and
Whereas, DPW should notify the Common Council of the City of Milwaukee of any such cost overruns, and changes in scope approved by DPW; and
Whereas, Funding for the construction of these projects will be included in future resolution; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is hereby authorized to execute the revised project agreement for the reconstruction of West Capitol Drive from North 60th Street to West Mayfair Road (STH 100) with State/Federal Aid under the WisDOT State Trunk Highway Program in two phases, a copy of which is attached to Common Council File 100024 and is incorporated by reference as though set forth in full.
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
LCG:amh
March 25, 2010
Reso W Captl (STH 190) M-Fai Rd - N 60 032510.rtf