Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $15,449,047 for a total estimated cost of these projects being $16,114,147.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Sub 2 Fiscal Note, 3. Fiscal Note, 4. Capital Grant Certification, 5. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
3/9/20102 MAYOR SIGNED   Action details Meeting details Not available
3/2/20102 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
2/18/20102 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
2/18/20102 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass4:0 Action details Meeting details Not available
2/18/20101 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual present: Mary Dziewiontkowski, Dept. of Public Works, Infra. Services Proposed Substitute A offered.
Pass4:0 Action details Meeting details Not available
2/15/20101 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
2/12/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
2/12/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
2/9/20100 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
091344
Version
SUBSTITUTE 2
Reference
051658
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $15,449,047 for a total estimated cost of these projects being $16,114,147.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $15,449,047. The total estimated cost of these projects is $16,114,147.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

2nd Aldermanic District

W. Caldwell Ct. - W. Medford Ave. to 475 feet west of W. Medford Ave. (WT410071031) File Number 051658: Relay water main. (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 -- $94,000). The total estimated cost for this project including the requested amount is $110,000. This project is anticipated to be completed during the 2010 construction season.

W. Custer Ave. - W. Fond du Lac Ave. to N. 83rd St. (WT410071032) File Number 051658: Relay water main. (Nonassessable Water Fund Budget Line 5010 -- $23,000; Nonassessable Water Fund Budget Line 6410 -- $402,000). The total estimated cost for this project including the requested amount is $450,000. This project is anticipated to be completed during the 2010 construction season.

W. Medford Ave. - W. Villard Ave. to W. Custer Ave. (WT410071030) File Number 051658: Relay water main. (Nonassessable Water Fund Budget Line 5010 -- $13,000; Nonassessable Water Fund Budget Line ...