File #: 091343    Version:
Type: Resolution Status: Passed
File created: 2/9/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/2/2010
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $150,000 for a total estimated cost of these projects being $1,713,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Fiscal Note, 3. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
3/9/20101 MAYOR SIGNED   Action details Meeting details Not available
3/2/20101 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
2/18/20101 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual present: Mary Dziewiontkowski, Dept. of Public Works, Infra. Services
Pass4:0 Action details Meeting details Not available
2/15/20101 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
2/12/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
2/12/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
2/9/20100 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

091343

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $150,000 for a total estimated cost of these projects being $1,713,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $150,000 with the total cost estimated to be $1,713,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

4th and 15th Aldermanic Districts

 

W. Cherry St. - N. 13th St. to N. 14th St. (SM495100042): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $66,000.  This project is anticipated to be completed during the 2010 construction season.

 

N. 14th St. - W. Cherry St. to W. Vliet St. (SM495100041): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2010 construction season.

 

5th Aldermanic District

 

N. 82nd St. - W. Keefe Ave. to 230 feet m/l north of W. Nash St. (WT410100020): Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $220,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 87th St. - W. Auer Ave. to W. Concordia Ave. (WT410100022): Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2010 construction season.

 

7th Aldermanic District

 

W. Fond du Lac Ave. - W. Melvina St. to W. Capitol Dr. (SM495100017): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $1,000).  The total estimated cost for this project including the requested amount is $166,000.  This project is anticipated to be completed during the 2010 construction season.

 

10th Aldermanic District

 

W. Vine St. - N. 56th St. to N. 58th St. (SM495100039): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $136,000.  This project is anticipated to be completed during the 2010 construction season.

 

N. 56th St. - W. Vine St. to 455 feet m/l south of W. Vine St. (SM495100040): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2010 construction season.

 

N. 58th St. - 315 feet south of W. Valley Forge Dr. to W. Valley Forge Dr. (WT410100023): Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $65,000.  This project is anticipated to be completed during the 2010 construction season.

 

City Wide

 

2010 Sanitary Bypass Pump Rehabilitation (SM497100101): Sanitary pump rehabilitation project. (Nonassessable Pump Repair -- $20,000).  The total estimated cost for this project including the requested amount is $500,000.  This project is anticipated to be completed during the 2010 construction season.

 

Indirect Account/Engineering Studies throughout the City of Milwaukee (SM493100001): (Nonassessable TSS Removal Fund -- $1,000).  The total estimated cost for this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2010 construction season.

 

Hales Corners

 

S. 124th St. - W. Cold Spring Rd. to W. Grange Ave. (WT410100021): Hydrant alteration. (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2011 construction season.

 

Suburban Plan Reviews

 

Review and Inspection (WT440070000): (Nonassessable Water Fund Budget Line 5010 -- $500; Nonassessable Water Fund Budget Line 6410 -- $4,500, Additional Funding).  The total estimated cost for this project including the requested amount is $45,000.  This project is anticipated to be completed during the 2010 construction season.

 

; and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Npr 8

02/12/10