powered help
header-left header-center header-right
File #: 091232    Version:
Type: Resolution Status: Passed
File created: 1/20/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/9/2010
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $78,700 for a total estimated cost of these projects being $727,700.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Fiscal Note, 3. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
2/16/20101 MAYOR SIGNED   Action details Meeting details Not available
2/9/20101 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
1/27/20101 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual present: Clark Wantoch, Dept. of Public Works, Infra. Services
Pass5:0 Action details Meeting details Not available
1/22/20101 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
1/22/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
1/20/20100 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
091232
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $78,700 for a total estimated cost of these projects being $727,700.
Analysis
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction. The City cost for engineering these projects is estimated to be $78,700 with the total cost estimated to be $727,700.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

5th Aldermanic District

W. Townsend St. - N. 92nd St. to N. 99th St. (ST211110140): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $15,000). The total estimated cost for this project including the requested amount is $260,000. This project is anticipated to be completed during the 2011 construction season.

N. 119th St. - W. Hampton Ave. to 1,600 feet m /l north of W. Hampton Ave. (SM495100035): Installing storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $228,...

Click here for full text