Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $606,535 for a total estimated cost of $969,900.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $606,535. The total estimated cost of these projects is $969,900.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
1st Aldermanic District
N. 19th Pl. - W. Olive St. to W. Congress St. (ST211180237) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $3,940; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $11,700. This project is anticipated to be completed during the 2023 construction season.
N. 19th St. - W. Fiebrantz Ave. to W. Olive St. (ST211220255) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,770; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $11,700. This project is anticipated to be completed during the 2023 construction season.
N. 44th St. - W. Villard Ave. to W. Custer Ave. (ST211220243) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $4,000; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $11,700. This project is anticipated to be completed during the 2023 construction season.
N. 45th St. - W. Eggert Pl. to W. Villard Ave. (ST211220248) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,040; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
5th Aldermanic District
N. 99th St. - W. Good Hope Rd. to W. Everts St. (ST211220103) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $5,420; Nonassessable Reconstruction Paving Fund -- $1,500). The total estimated cost for this project including the requested amount is $31,700. This project is anticipated to be completed during the 2023 construction season.
6th Aldermanic District
N. 14th St. - W. Melvina St. to W. Capitol Dr. (ST211220246) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,065; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
N. 16th St. - W. Vienna Ave. to W. Atkinson Ave. (ST211230111) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,525; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
N. 21st St. - W. Townsend St. to W. Keefe Ave. (ST211220247) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,330; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
W. Wright St. - N. 1st St. to N. 2nd St. (ST211230112) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $640; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $7,000. This project is anticipated to be completed during the 2023 construction season.
7th Aldermanic District
N. 40th St. - W. Ruby Ave. to W. Glendale Ave. (ST211230114) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,405; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
N. 46th St. - W. Auer Ave. to W. Concordia Ave. (ST211230115) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,730; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $10,900. This project is anticipated to be completed during the 2023 construction season.
N. 50th St. - W. Nash St. to W. Vienna Ave. (ST211230113) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,320; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
8th Aldermanic District
S. 23rd St. - W. Mitchell St. to W. Lapham St. (ST211230116) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $650; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $7,800. This project is anticipated to be completed during the 2023 construction season.
S. 24th St. - W. Mitchell St. to W. Lapham St. (ST211230117) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $565; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $7,800. This project is anticipated to be completed during the 2023 construction season.
S. 33rd St. - W. Pabst Ave. to W. Arthur Ave. (ST211220249) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $3,245; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $9,900. This project is anticipated to be completed during the 2023 construction season.
W. Lapham St. - S. 22nd St. to S. 25th St. (ST211230118) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,595; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $21,500. This project is anticipated to be completed during the 2023 construction season.
W. Orchard St. - S. 37th St. to S. 38th St. (ST211230119) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,110; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
10th Aldermanic District
N. 48th St. - W. Washington Blvd. to W. Lloyd St. (ST211220260) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $5,220; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $10,900. This project is anticipated to be completed during the 2023 construction season.
N. 57th St. - W. North Ave. to W. Meinecke Ave. (ST211220239) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,265; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
N. 58th St. - W. Center St. to W. Hadley St. (ST211180287) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,920; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
N. 61st St. - W. Clarke St. to W. Center St. (ST211220240) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,160; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
N. Hartung Ave. - N. 67th St. to W. Lisbon Ave. (ST211220241) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,995; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $13,000. This project is anticipated to be completed during the 2023 construction season.
13th Aldermanic District
W. Van Norman Ave. - S. Howell Ave. to S. 1st St. (ST211220250) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $730; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
14th Aldermanic District
Alley between W. Euclid Ave., W. Oklahoma Ave., S. 7th St., and S. 8th St. (ST212210105) File Number 211198: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary. (Assessable Alley Paving Fund - $57,190; Nonassessable Alley Paving Fund -- $129,000). The total estimated cost for this project including the requested amount is $360,000. This project is anticipated to be completed during the 2023 construction season.
S. 14th St. - W. Manitoba St. to W. Dakota St. (ST211230122) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,385; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $6,900. This project is anticipated to be completed during the 2023 construction season.
E. Montana St. - S. Quincy Ave. to S. Howell Ave. (ST211220229) File Number 221598: Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (5.5’ width of tree border area) and grading. (Assessable Reconstruction Paving Fund - $20,160; Nonassessable Reconstruction Paving Fund -- $319,000). The total estimated cost for this project including the requested amount is $360,000. This project is anticipated to be completed during the 2023 construction season.
15th Aldermanic District
N. 15th St. - W. North Ave. to W. Meinecke Ave. (ST211220252) Installing traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,660; Nonassessable Reconstruction Paving Fund -- $1,000). The total estimated cost for this project including the requested amount is $11,500. This project is anticipated to be completed during the 2023 construction season.
; and
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
Further Resolved That a portion of the speed hump projects will be utilizing ARPA (American Rescue Plan Act) funds: The project/grant number is RG1515236105; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That projects N. 19th Pl. (ST211180237), N. 19th St. (ST211220255), N. 44th St. (ST211220243), N. 45th St. (ST211220248), N. 99th St. (ST211220103), N. 14th St. (ST211220246), N. 16th St. (ST211230111), N. 21st St. (ST211220247), W. Wright St. (ST211230112), N. 40th St. (ST211230114), N. 46th St. (ST211230115), N. 50th St. (ST211230113), S. 23rd St. (ST211230116), S. 24th St. (ST211230117), S. 33rd St. (ST211220249), W. Lapham St. (ST211230118), W. Orchard St. (ST211230119), N. 48th St. (ST211220260), N. 57th St. (ST211220239), N. 58th St. (ST211180287), N. 61st St. (ST211220240), N. Hartung Ave. (ST211220241), W. Van Norman Ave. (ST211220250), Euclid Ave. Alley (ST212210105), S. 14th St. (ST211230122), E. Montana St. (ST211220229), N. 15th St. (ST211220252) will be billed after January 1, 2025, but not before 12 months after the project contract has been completed.