File #: 220871    Version:
Type: Resolution Status: Passed
File created: 10/11/2022 In control: COMMON COUNCIL
On agenda: Final action: 11/1/2022
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $232,000 for a total estimated cost of these projects being $4,196,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
220871
Version
Substitute 1
Reference
181588
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $232,000 for a total estimated cost of these projects being $4,196,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $232,000 with the total cost estimated to be $4,196,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

3rd Aldermanic District

E. Belleview Pl. - N. Maryland Ave. to N. Stowell Ave. (SM495220051) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund - $12,000). The total estimated cost of this project including the requested amount is $274,000. This project is anticipated to be completed during the 2023 construction season.

6th Aldermanic District

W. Concordia Ave. - N. 22nd St. to 155’ +/- East of N. 22nd St. (SM495220047) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund - $10,000). The total estimated cost of this project including the requested amount is $51,000. This project is anticipated to be completed during the 2023 construction season.

N. Hubbard St. - E. Wright St. to E. Center St. (SM495220050) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund - $15,000). The total estimated cost of this project including the requested amount is $363,000. This project is anticipated to be completed during the 2023 construction season.

7th Aldermanic District

N. 27th St. - W. Keefe Ave. (EXT...