File #: 220303    Version:
Type: Resolution Status: Passed
File created: 6/21/2022 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/12/2022
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $62,465 for a total estimated cost of $146,100.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. AD.pdf, 2. Signed AD, 3. Signed Letter.pdf, 4. Notice published 7/29/2022
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
7/29/20221 CITY CLERK PUBLISHED   Action details Meeting details Not available
7/15/20221 MAYOR SIGNED   Action details Meeting details Not available
7/12/20221 COMMON COUNCIL ADOPTEDPass11:0 Action details Meeting details Not available
6/29/20220 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Holly Rutenbeck - DPW - explained that the post card survey results are in favor. 1st Aldermanic District N. 33rd st. - W. Villard Ave. to W. Custer Ave. (ST211220141) Install traffic calming speed hump(s). Ald. Borkoswki moved approval. N. 38th st. - W. Custer Ave. to W. Sheridan Ave. (ST211220145) Install traffic calming speed hump(s). Ald. Hamilton moved approval. Ald. Dodd moved to reconsider the item at 9:22 am because one neighbor wants to testify. Neighbors in opposition: Robin Bean - 3463 N 38th St - said that there has been a request for a 4 way stop for 10 years now and that no minimum efforts have been made before. Ald. Hamilton moved approval. N. 40th st. - N. Hopkins st. to W. Villard Ave. (ST211220140) Install traffic calming speed hump(s). Ald. Hamilton moved approval. N. 48th St. — W. Luscher Ave. to W. Fairmount Ave. (ST211220163) Install traffic calming speed hump(s). Neighbors in Support: Nico Triggs - 4969 N 48th St - said that most of the neighbors are senior citizens and that they want to keep the street safe. Ald. Hamilton moved approval. N. 50th St. — W. Luscher Ave. to W. Fairmount Ave. (ST211220143) Install traffic calming speed hump(s). Ald. Hamilton moved approval. W. Carmen Ave. - N. 27th st. to N. 29th st. (ST211220162) Install traffic calming speed hump(s). Ald. Hamilton moved approval. N. Darien st - W. Cheyenne st. to W. vera Ave. (ST211220142) Install traffic calming speed hump(s). Ald. Hamilton moved approval. W. Lancaster Ave. - N. 42nd st. to N. Sherman Blvd. (ST211220123) Install traffic calming speed hump(s). Ald. Hamliton moved approval. 2nd Aldermanic District N. 61st St. — W. Marion St. to W. Congress St. (ST211220167) Install traffic calming speed hump(s). Ald. Borkowski moved approval. W. Stark st. - N. 60th st. to N. 61st st. (ST211220176) Install traffic calming speed hump(s). Ald. Hamilton moved approval. W. Thurston Ave. - N. 97th st. to N. 98th st. (ST211220151) Install traffic calming speed hump(s). Ms. Rutenbeck made the note for the record that no responses from the survey post card were received for this item. Ald. Dodd moved approval. 7th Aldermanic District N. 29th st. - W. Concordia Ave. to W. Townsend st. (ST211220154) Install traffic calming speed hump(s). Neighbors in Support: Marshall Robinson - 3368 N 29th St - said that the majority of the neighbors are seniors and children and that it is a street with lots of speeding issues. Ald. Borkowski moved approval. N. 49th st. - W. Hope Ave. to W. Marion st. (ST211220146) Install traffic calming speed hump(s). Neighbors in Support: Michael Grimm - 4205 N 49th St - said that a lot more is needed on Hope Av. as well. Ald. Stamper moved approval. N. 49th St. — W. Townsend St. to W. Keefe Ave. (ST211220153) Install traffic calming speed hump(s). Ald. Borkowski moved approval. N. 56th st. - W. Parkway Dr. to W. Hampton Ave. (ST211220150) Install traffic calming speed hump(s). Ald. Dodd moved approval. 10th Aldermanic District N. 53rd st. - W. Clarke st. to W. Center St. (ST211220195) Install traffic calming speed hump(s). Ald. Stamper moved approval. N. 58th st. - W. Wright st. to W. Clarke St. (ST211220169) Install traffic calming speed hump(s). Neighbors in Support: Christian - 3524 N 58th St- said that it is a long street without a stop sign. Ald. Borkowski moved approval. W. Potomac Ave. - N. 73rd st to W. Chapman Pl. (ST211220159) Install traffic calming speed hump(s). Neighbors in Opposition: Ms. Simms - 7342 W Potomac Av - said that the streets are in poor condition to have a speed hump instead of repaving it. Ald. Borkowski moved to hold the item to the call of chair. Ald. Borkowski moved approval of the file 220303 as amended.
Pass5:0 Roll call Meeting details Video Video
6/21/20220 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

220303

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $62,465 for a total estimated cost of $146,100.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $62,465.  The total estimated cost of these projects is $146,100.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

1st Aldermanic District

 

N. 33rd St. - W. Villard Ave. to W. Custer Ave. (ST211220141) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,575; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $12,500. This project is anticipated to be completed during the 2022 construction season.

 

N. 38th St. - W. Custer Ave. to W. Sheridan Ave. (ST211220145) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,390; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

N. 40th St. - N. Hopkins St. to W. Villard Ave. (ST211220140) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,505; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

N. 48th St. - W. Luscher Ave. to W. Fairmount Ave. (ST211220163) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $3,710; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $11,700. This project is anticipated to be completed during the 2022 construction season.

 

N. 50th St. - W. Luscher Ave. to W. Fairmount Ave. (ST211220143) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $3,325; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $12,400. This project is anticipated to be completed during the 2022 construction season.

 

W. Carmen Ave. - N. 27th St. to N. 29th St. (ST211220162) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,320; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

N. Darien St. - W. Cheyenne St. to W. Vera Ave. (ST211220142) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,430; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,500. This project is anticipated to be completed during the 2022 construction season.

 

W. Lancaster Ave. - N. 42nd St. to N. Sherman Blvd. (ST211220123) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $265; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

2nd Aldermanic District

 

N. 61st St. - W. Marion St. to W. Congress St. (ST211220167) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,245; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

W. Stark St. - N. 60th St. to N. 61st St. (ST211220176) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $755; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

W. Thurston Ave. - N. 97th St. to N. 98th St. (ST211220151) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $170; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,500. This project is anticipated to be completed during the 2022 construction season.

 

7th Aldermanic District

 

N. 29th St. - W. Concordia Ave. to W. Townsend St. (ST211220154) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,745; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

N. 49th St. - W. Hope Ave. to W. Marion St. (ST211220146) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,400; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

N. 49th St. - W. Townsend St. to W. Keefe Ave. (ST211220153) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,490; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

N. 56th St. - W. Parkway Dr. to W. Hampton Ave. (ST211220150) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $5,045; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $16,200. This project is anticipated to be completed during the 2022 construction season.

 

10th Aldermanic District

 

N. 53rd St. - W. Clarke St. to W. Center St. (ST211220195) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,165; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,300. This project is anticipated to be completed during the 2022 construction season.

 

N. 58th St. - W. Wright St. to W. Clarke St. (ST211220169) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,430; Nonassessable Reconstruction Paving Fund -- $1,500).  The total estimated cost for this project including the requested amount is $7,100. This project is anticipated to be completed during the 2022 construction season.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved That a portion of the speed hump projects will be utilizing ARPA (American Rescue Plan Act) funds:  The project/grant number is RG1515236103; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That projects N. 33rd St. (ST211220141), N. 38th St. (ST211220145), N. 40th St. (ST211220140), N. 48th St. (ST211220163), N. 50th St. (ST211220143), W. Carmen Ave. (ST211220162), N. Darien St. (ST211220142), W. Lancaster Ave. (ST211220123), N. 61st St. (ST211220167), W. Stark St. (ST211220176), W. Thurston Ave. (ST211220151), N. 29th St. (ST211220154), N. 49th St. (ST211220146), N. 49th St. (ST211220153), N. 56th St. (ST211220150), N. 53rd St. (ST211220195), N. 58th St. (ST211220169), will be billed after January 1, 2024, but not before 12 months after the project contract has been completed.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck/TW

Afr 14