powered help
header-left header-center header-right
File #: 220265    Version: 0
Type: Resolution Status: Passed
File created: 6/21/2022 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/12/2022
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute State/Municipal Agreements for a State-Let Highway Project with the Wisconsin Department of Transportation for the construction of Fond du Lac Avenue (STH 145); Bridge over 76th Street and Pedestrian Bridge, and to set up funds for construction at an estimated total cost of $5,036,000 with an estimated City share of $17,000 and a grantor share of $5,019,000.
Sponsors: THE CHAIR
Indexes: BRIDGES, INTERGOVERNMENTAL AGREEMENTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. State Municipal Maintenance Agreement, 2. State Municipal Financial Agreement, 3. Resolution Certification Comptroller's Office

Number

220265

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution directing the Commissioner of Public Works to execute State/Municipal Agreements for a State-Let Highway Project with the Wisconsin Department of Transportation for the construction of Fond du Lac Avenue (STH 145); Bridge over 76th Street and Pedestrian Bridge, and to set up funds for construction at an estimated total cost of $5,036,000 with an estimated City share of $17,000 and a grantor share of $5,019,000. 

Analysis

This resolution directs the Commissioner of Public Works to execute State/Municipal Agreements with the Wisconsin Department of Transportation for the construction of Fond du Lac Avenue (STH 145); Bridge over 76th Street and Pedestrian Bridge.  The State/Municipal Agreements provide for 90 percent Federal and State aid and 10 percent local cost sharing for street lighting costs.  The total estimated cost of this project is $5,036,000 with an estimated City share of $17,000 and a grantor share of $5,019,000. 

Body

Whereas, Project agreements have been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the construction of Fond du Lac Avenue (STH 145); Bridge over 76th Street and Pedestrian Bridge, with Federal and State aid under the State Highway Rehabilitation Program; and

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is hereby authorized to execute the agreement for the programming, design, and construction of the aforementioned connecting highway project with Federal and/or State aid, copies of which are attached to Common Council Resolution File Number _________, and are incorporated into this resolution by reference as though set forth in full; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project Grant Chartfield Values for construction for the project (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

State I.D. 1360-13-70

Fond du Lac Avenue (STH 145); Bridge over 76th Street and Pedestrian Bridge. 

 

City Share

ST320220000

Fund 0333

$17,000

 

Grantor Reimbursable Funds

SP032220100

Fund 0306

$0

 

Grantor Non-Reimbursable Funds

$5,019,000

 

Estimated Total Engineering $3,635,000

Total Engineering Previously Authorized $0

Current Estimated Cost of Total Project Including this Resolution $5,036,000

Original Estimate Cost of Total Project $$5,036,000

 

Further Resolved, That the City Engineer is hereby authorized to approve and make periodic payments to the WisDOT upon receipt of invoices for the City’s share of the project costs.

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

DAVID J TAPIA:C. Murphy

June 14, 2022