Number
091162
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the City Comptroller to transfer additional funds to various State and Federal Aid project subaccounts for the estimated remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering and review costs totaling $164,864.73, City share is $59,801.48 and the Grantor’s share is $105,063.25.
Analysis
This resolution authorizes the City Comptroller to transfer funds to the previously established subaccounts for the remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering and review costs in the amount of $164,864.73. The City of Milwaukee’s share is $59,801.48 and the Grantor share is $105,063.25.
Body
Whereas, The Common Council has previously adopted resolutions authorizing the City Comptroller to transfer funds to various State and Federal Aid project subaccounts (ARRA and ARRA related) for preliminary engineering and review; and
Whereas, Additional planning and review during the design stage have resulted in increased costs charged against the projects; and
Whereas, Additional funds are, therefore, necessary for the estimated remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering and review costs for the projects; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized and directed to transfer funds to the project grant chartfields as follows:
Aldermanic Districts 3 and 6
Project Grant Value
State I.D. 2059-00-01
ST320042001
East/West Keefe Avenue - North 7th Street to North Humboldt Boulevard
City share Non-Assessable Paving
ST320100000
Fund 0333
$5,816.70
Grantor Non-Reimbursable Paving
$23,266.81
Previously authorized for preliminary engineering and review: $255,060.00
Current estimated cost of total project including this resolution: $2,931,916.25
Original estimated cost of total project (Resolution #040400): $1,844,000.00
Aldermanic Districts 4 and 6
Project Grant Value
State I.D. 2057-01-00
ST520091101
West Winnebago Street - North 8th Street to North 7th Street
City Share Non-Assessable Paving
ST320100000
Fund 0333
$21,152.00
Previously authorized for engineering review (ARRA): $150,000.00
Current estimated cost of total project including this resolution: $951,152.00
Original estimated cost of total project (Resolution #090538): $910,000.00
Aldermanic Districts 4 and 12
Project Grant Value
State I.D. 2245-01-00
ST320021301
South 2nd Street - West National Avenue to Menomonee River
City Share Non-Assessable Paving
ST320100000
Fund 0333
$6,083.14
Grantor Share Non-Reimbursable Paving
$24,332.56
Previously authorized for preliminary engineering: $341,324.12
Current estimated cost of total project including this resolution: $2,402,246.05
Original estimated cost of total project (Resolution #010810): $1,832,420.00
Aldermanic District 6
Project Grant Value
State I.D. 2445-07-00
ST520091401
East/West North Avenue - Dr. Martin L. King, Jr. Dr. to North Booth Street
City Share Non-Assessable Paving
ST320100000
Fund 0333
$4,670.29
Grantor Share Non-Reimbursable Paving
$18,681.18
Previously authorized for engineering review (ARRA): $60,000.00
Current estimated cost of total project including this resolution: $2,878,451.47
Original estimated cost of total project (Resolution #081512): $1,929,200.00
Aldermanic District 12
Project Grant Value
State I.D. 2615-00-02
ST520090101
South Cesar E. Chavez Dr. - West Piece Street to West Greenfield Avenue
City Share Non-Assessable Paving
ST320100000
Fund 0333
$12,383.67
Previously authorized for engineering review (ARRA): $159,500.00
Current estimated cost of total project including this resolution: $1,306,883.67
Original estimated cost of total project (Resolution #090194): $1,250,000.00
Project Grant Value
State I.D. 2505-08-00
ST520091601
South 13th Street - West Cleveland Avenue to West Windlake Avenue
City Share Non-Assessable Paving
ST320100000
Fund 0333
$3,729.78
Grantor Share Non-Reimbursable Paving
$14,919.12
Previously authorized for engineering review (ARRA): $60,000.00
Current estimated cost of total project including this resolution: $2,610,378.90
Original estimated cost of total project (Resolution #081512): $2,280,500.00
Aldermanic Districts 12 and 14
Project Grant Value
State I.D. 2219-00-00
ST320042201
South 1st Street - West Lincoln Avenue to West Kinnickinnic Avenue
City of Milwaukee Share Non-Assessable Paving
ST320100000
Fund 0333
$5,965.90
Grantor Share Non-Reimbursable Paving $23,863.58
Previously authorized for preliminary engineering: $203,500.00
Current estimated cost of total project including this resolution: $2,066,726.05
Original estimated cost of total project (Resolution #040400): $1,562,000.00
Summary of projects in this resolution:
City Share Non-Assessable Paving (0333): $59,801.48
Grantor Non-Reimbursable Paving: $105,063.25
Resolution total: $164,864.73
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
LG:amh
December 15, 2009