File #: 091129    Version:
Type: Resolution Status: Passed
File created: 12/22/2009 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 1/20/2010
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $265,000 for a total estimated cost of these projects being $8,370,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Fiscal note, 3. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
1/29/20101 MAYOR SIGNED   Action details Meeting details Not available
1/20/20101 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
1/6/20101 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual present: Clark Wantoch, Dept. of Public Works, Infrastructure Services
Pass5:0 Action details Meeting details Not available
12/23/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
12/22/20090 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

091129

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $265,000 for a total estimated cost of these projects being $8,370,000.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $265,000 with the total cost estimated to be $8,370,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

1st Aldermanic District

 

W. Hopkins St. - N. 34th St. to N. 35th St. (ST211110131): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $8,000).  The total estimated cost for this project including the requested amount is $110,000.  This project is anticipated to be completed during the 2011 construction season.

 

2nd Aldermanic District

 

W. Flagg Ave. - N. 96th St. to N. 98th St. (ST211110130): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000).  The total estimated cost for this project including the requested amount is $110,000.  This project is anticipated to be completed during the 2011 construction season.

 

W. Winfield Ave. - A point east of N. 89th St. to N. 90th St. (ST211110136): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $8,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 67th St. - W. Marion St. to W. Congress St. (ST211110108): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2011 construction season.

 

2nd and 10th Aldermanic Districts

 

N. 65th St. - W. Melvina St. to W. Capitol Dr. (ST211110107): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $65,000.  This project is anticipated to be completed during the 2011 construction season.

 

3rd Aldermanic District

 

E. Back Bay - A point east of N. Terrace Ave. to N. Terrace Ave. (ST211110128): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2011 construction season.

 

5th Aldermanic District

 

W. Nash St. - N. 96th St. to a point west of N. 100th St. (West City Limits) (ST211110133): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2011 construction season.

 

W. Townsend St. - N. 76th St. to N. 82nd St. (ST211110134): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $16,000).  The total estimated cost for this project including the requested amount is $235,000.  This project is anticipated to be completed during the 2011 construction season.

 

W. Townsend St. - N. 92nd St. to N. 99th St. (ST211110136): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $260,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 79th St. - W. Keefe Ave. to W. Nash St. (ST211110138): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $13,000).  The total estimated cost for this project including the requested amount is $180,000.  This project is anticipated to be completed during the 2011 construction season.

 

Alley between W. Keefe Ave., W. Lisbon Ave., N. 91st St., and N. 92nd St. (ST21210116): Paving the alley with concrete.  Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $6,000).  The total estimated cost for this project including the requested amount is $170,000.  This project is anticipated to be completed during the 2010 construction season.

 

7th Aldermanic District

 

N. 41st St. - W. Congress St. to W. Ruby Ave. (ST211110137): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $6,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2011 construction season.

 

8th Aldermanic District

 

W. Lapham St. - S. Layton Blvd. to S. 29th St. (ST211110132): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $6,000).  The total estimated cost for this project including the requested amount is $70,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 50th St. - W. Oklahoma Ave. to W. Cleveland Ave. (ST211110106): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $19,000).  The total estimated cost for this project including the requested amount is $280,000.  This project is anticipated to be completed during the 2011 construction season.

 

9th Aldermanic District

 

W. County Line Rd. - N. 68th St. to N. 91st St. (ST211100132) File Number 090511: Paving the roadway with asphalt (Rural cross section). Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $25,000, Additional Funds).  The total estimated cost for this project including the requested amount is $2,300,000.  This project is anticipated to be completed during the 2010 construction season.

 

W. County Line Rd. - N. 91st St./N. Swan Rd. to N. 124th St./N. Wasaukee Rd. (ST211100131) File Number 090511: Paving the roadway with asphalt (Rural cross section). Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $25,000, Additional Funds).  The total estimated cost for this project including the requested amount is $2,900,000.  This project is anticipated to be completed during the 2010 construction season.

 

10th Aldermanic District

 

W. Main St. - S. Hawley Rd. to S. 70th St. (ST211110139): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $26,000).  The total estimated cost for this project including the requested amount is $390,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 60th St. - W. Dickinson St. to W. Main St. (ST211030113): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $4,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 63rd St. - W. Stack Dr. to W. Cleveland Ave. (ST211110110): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $9,000).  The total estimated cost for this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 66th St. - W. Euclid Ave. to W. Oklahoma Ave. (ST21100118): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $6,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2011 construction season.

 

13th Aldermanic District

 

W. Euclid Ave. - S. 16th St. to S. 20th St. (ST211110129): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $6,000).  The total estimated cost for this project including the requested amount is $130,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 23rd St. - W. Edgerton Ave. to W. Carpenter Ave. (ST211110109): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $11,000).  The total estimated cost for this project including the requested amount is $160,000.  This project is anticipated to be completed during the 2011 construction season.

 

14th Aldermanic District

 

E. Potter Ave. - S. Logan Ave. to S. Kinnickinnic Ave. (ST211110135): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $16,000).  The total estimated cost for this project including the requested amount is $225,000.  This project is anticipated to be completed during the 2011 construction season.

 

Alley between S. Austin St., S. Brisbane Ave., E. Euclid Ave., and E. Oklahoma Ave. (ST212050137): Paving the alley with concrete.  Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2010 construction season.

 

; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Apr 6