File #: 211749    Version:
Type: Resolution Status: Passed
File created: 3/1/2022 In control: COMMON COUNCIL
On agenda: Final action: 3/22/2022
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,137,000 for a total estimated cost of these projects being $5,568,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Proposed Substitute A

Number

211749

Version

Substitute 1

Reference

201552

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,137,000 for a total estimated cost of these projects being $5,568,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $5,137,000.  The total estimated cost of these projects is $5,568,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

1st Aldermanic District

 

N. 31st St. - W. Atkinson Ave. to W. Glendale Ave. (WT410220655) File Number 201552: Relaying water main and Lead replacement of service.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $105,000).  The total estimated cost of this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. 32nd St. - W. Hampton Ave. to 200’ North of W. Hampton Ave. (WT410220634) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $120,000).  The total estimated cost of this project including the requested amount is $135,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Glendale Ave. - N. 30th St. to N. 32nd St. (WT410220654) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $195,000).  The total estimated cost of this project including the requested amount is $210,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Hampton Ave. -N. 32nd St. to 250’ West of N. 32nd St. (WT410220633) File Number 201552: Water main abandonment.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $45,000).  The total estimated cost of this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. Hopkins St. - 70’ +/- South of Rohr Ave to W Custer Ave. (SM495210111) File Number: 211343. Relaying storm sewer and lining storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $169,000).  The total estimated cost of this project including the requested amount is $181,000.  This project is anticipated to be completed during the 2022 construction season.

 

2nd Aldermanic District

 

N. 54th St./ W. Maxwell Pl. - W. Capitol Dr. to W. Fond Du Lac Ave. (WT410220672) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $300,000).  The total estimated cost of this project including the requested amount is $320,000.  This project is anticipated to be completed during the 2022 construction season.

 

5th Aldermanic District

 

N. 85th St. - W. Capitol Dr. to W. Olive St. (WT410220673) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $370,000).  The total estimated cost of this project including the requested amount is $395,000.  This project is anticipated to be completed during the 2022 construction season.

 

 

N. 88th St. - N. Colgate Cir. to W. Marion St. (WT410220675) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $230,000).  The total estimated cost of this project including the requested amount is $250,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. 100th St. - W. Capitol Dr. to W. Grantosa Dr. (WT410220600) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $400,000).  The total estimated cost of this project including the requested amount is $420,000.  This project is anticipated to be completed during the 2022 construction season.

 

 

W. Fiebrantz Ave. - N. 82nd St. to N. 84th St. (WT410220677) File Number 201552: Water main extension.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $180,000).  The total estimated cost of this project including the requested amount is $195,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Grantosa Dr. - 225’ East of N. 100th St. to N. 100th St. (WT410220614) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $70,000).  The total estimated cost of this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Olive St. - N. 85th St. to N. 88th St. (WT410220674) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $270,000).  The total estimated cost of this project including the requested amount is $290,000.  This project is anticipated to be completed during the 2022 construction season.

 

6th Aldermanic District

 

N. 1st St. - E./W. Meinecke Ave. to E./W. Wright St. (SM495210112) File Number 211343:  Combined sewer relay and lining. (Nonassessable Sewer Maintenance Relay Fund -- $325,000).  The total estimated cost of this project including the requested amount is $340,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. 9th St. - W. Vliet St. to W. Somers St. (WT410220629) File Number 201552: Water main abandonment.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost of this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2022 construction season.

 

E. Clarke St. - N. 1st St. to N. Hubbard St. (WT410220649) File Number 201552: Relaying water main and lead replacement of service.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $265,000).  The total estimated cost of this project including the requested amount is $280,000.  This project is anticipated to be completed during the 2022 construction season.

 

 

7th Aldermanic District

 

N. 23rd St. - W. Chambers St. to W. Burleigh St. (SM495210071) File Number 211086:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $247,000).  The total estimated cost of this project including the requested amount is $259,000.  This project is anticipated to be completed during the 2022 construction season.

N. 36th St. - 310’ +/- South of W. Chambers St. to W. Chambers St. (SM495210034) File Number 210059:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $84,000).  The total estimated cost of this project including the requested amount is $96,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Burleigh St. - N. 21st St. to N. 23rd St. (SM495210072) File Number 211086:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $169,000).  The total estimated cost of this project including the requested amount is $181,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Cawker Pl. - N. 30th St. to 360’ West of N 30th St. (SM495210048) File Number: 210701. Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $58,000).  The total estimated cost of this project including the requested amount is $68,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Chambers St. - N. 37th St. to 135’ West of N 39th St. (SM495210049) File Number: 210701. Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $99,000).  The total estimated cost of this project including the requested amount is $111,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Locust St. - N. 35th St. to 140’ +/- West of N. 36th St. (SM495210041) File Number 210701:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $99,000).  The total estimated cost of this project including the requested amount is $111,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Nash St. - N. 38th St. to 160’ +/- West of N. 38th St. (SM495210114) File Number 211343:  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $37,000).  The total estimated cost of this project including the requested amount is $47,000.  This project is anticipated to be completed during the 2022 construction season.

 

9th Aldermanic District

 

N. 78th St. - W. Acacia St. to W. Casper St. (WT410220624) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $315,000).  The total estimated cost of this project including the requested amount is $335,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Acacia St. - N. 77th St. to N. 80th St. (WT410220623) File Number 201552: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $310,000).  The total estimated cost of this project including the requested amount is $330,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Casper St. - N. 77th St. to N. 78th St. (WT410220625) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $90,000).  The total estimated cost of this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2022 construction season.

 

10th Aldermanic District

 

N. 47th St. - W. Vliet St. to W. Cherry St. (SM495210110) File Number: 211343. Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $138,000).  The total estimated cost of this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2022 construction season.

 

12th Aldermanic District

 

W. Rogers St. - S. 13th St. to S. 14th St. (SM495210083) File Number 211199:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $122,000).  The total estimated cost of this project including the requested amount is $134,000.  This project is anticipated to be completed during the 2022 construction season.

 

14th Aldermanic District

 

S. Herman St. - E. Saveland Ave. to E. Howard Ave. (WT410220628) File Number 201552: Relaying water main and lead replacement of service.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $310,000).  The total estimated cost of this project including the requested amount is $330,000.  This project is anticipated to be completed during the 2022 construction season.

 

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck/MSA

Nfr9Sub

3/4/2022