File #: 211746    Version:
Type: Resolution Status: Passed
File created: 3/1/2022 In control: COMMON COUNCIL
On agenda: Final action: 3/22/2022
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $59,025 for a total estimated cost of $188,300.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. AD.pdf, 2. Signed Letter.pdf, 3. Signed Ad.pdf, 4. Motion by Ald Hamilton, 5. Notice published 4/8/2022
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/8/20222 CITY CLERK PUBLISHED   Action details Meeting details Not available
3/29/20222 MAYOR SIGNED   Action details Meeting details Not available
3/22/20222 COMMON COUNCIL AMENDED

Minutes note: Ald. Hamilton moved to amend the file to add the following text: In the 1st aldermanic district N. 37 Street.: W. Silver Spring Dr. to W. Thurston Ave. (211210203) Install traffic calming speed hump(s) (Prevailed 14-0)
Pass14:0 Action details Meeting details Video Video
3/22/20222 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
3/9/20221 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: 1st Aldermanic District N. 14th St.- W. Capitol Dr. to W. Fiebrantz Ave. (ST211210252) Install traffic calming speed hump(s). Grant, by Ald. Borkowski. Prevailed. 4-0 (Ald. Perez excused) N. 21st St.- W.Olive St. toW. Congress St. (ST211210254) Install traffic calming speed hump(s). Grant, by Ald. Borkowski. Prevailed. 4-0 (Ald. Perez excused) N. 37th St.- W. Silver Spring Dr. to W. Thurston Ave. (ST211210203) Install traffic calming speed hump(s). Scott Endergton - 5635 N. 37th St. -would like to see the street replaced as it has degraded over time. This is also a fire lane. Sarah Bellehumeur - 5634 N. 37th St. - supports a speed hump due to the high traffic speed and the heavy trucks going down the street. Hold to the call of the chair, by Ald. Borkowski. Prevailed. 4-0 (Ald. Perez excused) N. 54th St.- W. Villard Ave. to W. Custer Ave. {ST211210204) Install traffic calming speed hump(s). Grant, by Ald. Perez. Prevailed. 5-0 2nd Aldermanic District N. 63rd St.- W. Congress St. to W. Ruby Ave. (ST211210243) Install traffic calming speed hump(s). Grant, by Ald. Perez. Prevailed. 5-0 N. 63rd St.- W. Hope Ave. to W. Marion St. (ST211210244) Install traffic calming speed hump(s). Granb, by Ald. Perez. Prevailed. 5-0 N. 69th St.- W. Hope Ave. to W. Marion St. (ST211210246) Install traffic calming speed hump(s). Grant, by Ald. Borkowski. Prevailed. 5-0 5th Aldermanic District W. Bobolink Ave.- W. Appleton Ave. toN. 114th St. (ST211210185) Install traffic calming speed hump(s). citizen - objects to the speed humps Grant, by Ald. Borkowski. Prevailed. 5-0 6th Aldermanic District N. 6th St. - W. Meinecke Ave. to W. Wright St. (ST211210247) Install traffic calming speed hump(s). Grant, by Ald. Zamarripa. Prevailed. 5-0 N. 6th St.- W. Center St. toW. Hadley St. (ST211210248) Install traffic calming speed hump(s). Grant, by Ald. Stamper. Prevailed. 5-0 6th and 7th Aldermanic Districts N. 24th Pl.- W. Nash St. to W. Vienna Ave. (ST211190177) Install traffic calming speed hump(s). Grant, by Ald. Borkowski. Prevailed. 5-0 7th Aldermanic District N. 44th St.- W. Chambers St. to W. Burleigh St. (ST211210265) Install traffic calming speed hump(s). Grant, by Ald. Perez. Prevailed. 5-0 W. Auer Ave.- N. 25th St. to N. 26th St. (ST211210266) Install traffic calming speed hump(s). Grant, by Ald. Stamper. Prevailed. 5-0 9th Aldermanic District N. 52nd St.- W. Mill Rd. to W. Hassel Ln. (ST211180163) Install traffic calming speed hump(s). Grant, by Ald. Zamarripa. Prevailed. 5-0 10th Aldermanic District W. Michigan St. - N. 91st St. to N. 93rd St. (ST211210274) Install traffic calming speed hump(s). Elizabeth Kirkman - do need speed humps but there is a lack of coordination with street/sewer/water main work. Grant, by Ald. Perez. Prevailed. 5-0 15th Aldermanic District W. Clarke St.- N. 11th St. to N. 12th St. (ST211210291) Install traffic calming speed hump(s). Grant, by Ald. Stamper. Prevailed. 5-0 W. Hadley St.- N. 41st St. to N. Grant Blvd. (ST211210293) Install traffic calming speed hump(s). Grant, by Ald. Stamper. Prevailed. 5-0 W. Wright St.- N. Sherman Blvd. to N. 47th St. (ST211210292) Install traffic calming speed hump(s). Grant, by Ald. Stamper. Prevailed. 5-0
Pass5:0 Action details Meeting details Not available
2/1/20220 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

211746

Version

SUBSTITUTE 2

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $59,025 for a total estimated cost of $188,300.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $59,025.  The total estimated cost of these projects is $188,300.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

1st Aldermanic District

 

N. 14th St. - W. Capitol Dr. to W. Fiebrantz Ave. (ST211210252) Install traffic calming speed hump(s).  (Assessable Reconstruction Paving Fund - $1,945; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $6,600.  This project is anticipated to be completed during the 2022 construction season.

 

N. 21st St. - W. Olive St. to W. Congress St. (ST211210254) Install traffic calming speed hump(s).  (Assessable Reconstruction Paving Fund - $3,635; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $15,700.  This project is anticipated to be completed during the 2022 construction season.

 

N. 37th St. - W. Silver Spring Dr. to W. Thurston Ave. (ST211210203) Install traffic calming speed hump(s).  (Assessable Reconstruction Paving Fund - $2,825; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $13,300.  This project is anticipated to be completed during the 2022 construction season.

 

N. 54th St. - W. Villard Ave. to W. Custer Ave. (ST211210204) Install traffic calming speed hump(s).  (Assessable Reconstruction Paving Fund - $4,670; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $15,900.  This project is anticipated to be completed during the 2022 construction season.

 

2nd Aldermanic District

 

N. 63rd St. - W. Congress St. to W. Ruby Ave. (ST211210243) Install traffic calming speed hump(s).  (Assessable Reconstruction Paving Fund - $2,450; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $6,600.  This project is anticipated to be completed during the 2022 construction season.

 

N. 63rd St. - W. Hope Ave. to W. Marion St. (ST211210244) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,500; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $6,600.  This project is anticipated to be completed during the 2022 construction season.

 

N. 69th St. - W. Hope Ave. to W. Marion St. (ST211210246) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,385; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $6,600.  This project is anticipated to be completed during the 2022 construction season.

 

5th Aldermanic District

 

W. Bobolink Ave. - W. Appleton Ave. to N. 114th St. (ST211210185) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $10,750; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $20,600.  This project is anticipated to be completed during the 2022 construction season.

 

6th Aldermanic District

 

N. 6th St. - W. Meinecke Ave. to W. Wright St. (ST211210247) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,060; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $7,200.  This project is anticipated to be completed during the 2022 construction season.

 

N. 6th St. - W. Center St. to W. Hadley St. (ST211210248) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,175; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $7,200.  This project is anticipated to be completed during the 2022 construction season.

 

6th and 7th Aldermanic Districts

 

N. 24th Pl. - W. Nash St. to W. Vienna Ave. (ST211190177) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,930; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $6,600.  This project is anticipated to be completed during the 2022 construction season.

 

7th Aldermanic District

 

N. 44th St. - W. Chambers St. to W. Burleigh St. (ST211210265) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $2,365; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $6,400.  This project is anticipated to be completed during the 2022 construction season.

 

W. Auer Ave. - N. 25th St. to N. 26th St. (ST211210266) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $960; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $6,400.  This project is anticipated to be completed during the 2022 construction season.

 

9th Aldermanic District

 

N. 52nd St. - W. Mill Rd. to W. Hassel Ln. (ST211180163) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $6,095; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $20,600.  This project is anticipated to be completed during the 2022 construction season.

 

10th Aldermanic District

 

W. Michigan St. - N. 91st St. to N. 93rd St. (ST211210274) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,805; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $11,200.  This project is anticipated to be completed during the 2022 construction season.

 

15th Aldermanic District

 

W. Clarke St. - N. 11th St. to N. 12th St. (ST211210291) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $200; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $7,800.  This project is anticipated to be completed during the 2022 construction season.

 

W. Hadley St. - N. 41st St. to N. Grant Blvd. (ST211210293) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $270; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $6,200.  This project is anticipated to be completed during the 2022 construction season.

 

W. Wright St. - N. Sherman Blvd. to N. 47th St. (ST211210292) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $1,005; Nonassessable Reconstruction Paving Fund -- $500).  The total estimated cost for this project including the requested amount is $16,800.  This project is anticipated to be completed during the 2022 construction season.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved That a portion of the speed hump projects will be utilizing ARPA (American Rescue Plan Act) funds:  The project/grant number is RG1515236101; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That projects N. 14th St. (ST211210252), N. 21st St. (ST211210254), N. 54th St. (ST211210204), N. 63rd St. (ST211210243), N. 63rd St. (ST211210244), N. 69th St. (ST211210246), W. Bobolink Ave. (ST211210185), N. 6th St. (ST211210247), N. 6th St. (ST211210248), N. 24th Pl. (ST211190177), N. 44th St. (ST211210265), W. Auer Ave. (ST211210266), N. 52nd St. (ST211180163), W. Michigan St. (ST211210274), W. Clarke St. (ST211210291), W. Hadley St. (ST211210293), and W. Wright St. (ST211210292) will be billed after January 1, 2024, but not before 12 months after the project contract has been completed.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck

AFR 9

3/9/2022