File #: 090891    Version:
Type: Resolution Status: Passed
File created: 11/3/2009 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 1/20/2010
Effective date:    
Title: Substitute resolution authorizing the Commissioner of Public Works to utilize the most appropriate method for contracting the City Hall Foundation Restoration Project.
Sponsors: THE CHAIR
Indexes: CITY HALL, HISTORIC PRESERVATION, PUBLIC BUILDINGS
Attachments: 1. Fiscal note, 2. E-mail from Commissioner of Public Works, 3. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
1/29/20102 MAYOR SIGNED   Action details Meeting details Not available
1/20/20102 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
1/6/20102 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
1/6/20102 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
1/6/20101 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individuals present: Venu Gupta, Dept. of Public Works Ron Schoeneck, Dept. of Public Works Ald. Wade offered proposed substitute A.
Pass5:0 Action details Meeting details Not available
12/23/20091 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
12/9/20091 PUBLIC WORKS COMMITTEE HELD TO CALL OF THE CHAIR

Minutes note: Held until later in the meeting. Individuals present: Jeff Mantes, Commissioner of Public Works Ron Schoeneck, Dept. of Public Works PowerPoint presentation given by Mr. Mantes Hold one cycle
Pass5:0 Action details Meeting details Not available
12/4/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
12/4/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
12/3/20091 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
11/18/20090 PUBLIC WORKS COMMITTEE HELD TO CALL OF THE CHAIRPass4:0 Action details Meeting details Not available
11/10/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/29/20090 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
090891
Version
SUBSTITUTE 2
Reference

Sponsor
THE CHAIR
Title
Substitute resolution authorizing the Commissioner of Public Works to utilize the most appropriate method for contracting the City Hall Foundation Restoration Project.
Analysis
This resolution authorizes the Commissioner of Public Works to utilize the most appropriate method for contracting the City Hall Foundation Restoration Project. Should traditional competitive bidding (design/bid/build process) prove to be impossible or impracticable, this resolution authorizes the use of an alternate design/build delivery method. In addition, the resolution provides a system of checks and balances for protecting the City’s best interests in this project.
Body
Whereas, Significant repair and restoration work is needed to address aging-related deterioration of key exterior elements of City Hall, including wood foundation piles, pile caps, a water recharge system, below grade hollow sidewalk walls, and structural concrete beams and sidewalk; and

Whereas, Access to restore City Hall’s wood pile foundation system will specifically require the removal and repair/restoration of the hollow sidewalk on the east and west sides of City Hall and the repair/restoration of the water recharge system that preserves the submerged wood pile system; and

Whereas, A traditional design/bid/build process, with a designer selected through a Request For Proposal and a contractor chosen through competitive bidding, is typically mandated on such public works projects; and

Whereas, It may, however, be impossible or impracticable to draft contract documents to contract the City Hall Foundation Restoration Project via traditional competitive bidding due to the uncertainty of the scope of work necessary to stabilize the wood pile foundation system; and

Whereas, An alternate design/build process, whereby a single contract is awarded through Request For Proposal protocol, may be the most feasible and practical method ...

Click here for full text