powered help
header-left header-center header-right
File #: 211167    Version: 0
Type: Resolution Status: Passed
File created: 11/23/2021 In control: COMMON COUNCIL
On agenda: Final action: 12/14/2021
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute a 1st Revision State/Municipal Agreement with the Wisconsin Department of Transportation to fund design, construction, and procurement costs for the Bike Share Phase 2 project.
Sponsors: THE CHAIR
Indexes: BICYCLES, CYCLING, INTERGOVERNMENTAL AGREEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. 2190-06-04-74-84 Bikeshare2Rev 2021 0607.pdf, 2. Resolution Certification from Comptroller's

Number

211167

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution directing the Commissioner of Public Works to execute a 1st Revision State/Municipal Agreement with the Wisconsin Department of Transportation to fund design, construction, and procurement costs for the Bike Share Phase 2 project.

Analysis

This resolution directs the Commissioner of Public Works to execute a 1st Revision State/Municipal Agreement with the Wisconsin Department of Transportation for the design, construction, and procurement of Bike Share Phase 2.  The State/Municipal Agreement provides for 80 percent Federal and State aid and 20 percent local cost sharing.  The revised total estimated cost of this project is $1,899,990 with a grantor share of $1,519,992 and a City share of $379,998.  This resolution also directs the City Comptroller to transfer funds from construction to procurement at a new estimated procurement cost of $1,551,438.96 with an estimated City share of $310,287.79 and a grantor share of $1,241,151.17, and a new estimated construction cost of $75,962.04 with an estimated City share of $15,192.41 and a grantor share of $60,769.63.

 

Body

Whereas, Project agreements have been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the Bike Share Phase 2 project under the 2016-2020 Congestion Mitigation Air Quality program; and

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is hereby authorized to execute the 1st Revision State/Municipal Agreement with the Wisconsin Department of Transportation for the design, construction, and procurement of the aforementioned Bike Share Phase 2 project with Federal and/or State aid, copies of which are attached to Common Council Resolution File Number _________, and are incorporated into this resolution by reference as though set forth in full; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project Grant Chartfield Values for design, construction, and procurement for the project (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

State I.D. 2190-06-74

ST320161110

Bike Share Phase 2, 26 Stations, Milwaukee County

Construction

 

City Share

ST320161110

Fund 0333

($60,441.59)

 

Grantor Reimbursable Funds

ST320161110

Fund 0306

(236,864.04)

 

Grantor Non-Reimbursable Funds

($4,903.33)

 

Estimated Total Construction ($302,208.96)

 

Total Construction Previously Authorized $378,171

Current Estimated Cost of Total Project Including this Resolution $1,899,990

Original Estimate Cost of Total Project (Resolution 160625) $1,899,990

 

State I.D. 2190-06-84

ST320161180

Bike Share Phase 2, 26 Stations, Milwaukee County

Procurement

 

City Share

ST320161180

Fund 0333

$60,441.79

 

Grantor Reimbursable Funds

ST320161180

Fund 0306

$241,767.17

 

Estimated Total Procurement $302,208.96

 

Total Procurement Previously Authorized $1,249,230

Current Estimated Cost of Total Project Including this Resolution $1,899,990

Original Estimate Cost of Total Project (Resolution 160625) $1,899,990

 

 Further Resolved, That the City Engineer is hereby authorized to approve and make periodic payments to the WisDOT upon receipt of invoices for the City’s share of the project costs.

 

 

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

KATE RIORDAN:C. Murphy

November 5, 2021