File #: 210999    Version: 0
Type: Resolution Status: Passed
File created: 11/2/2021 In control: COMMON COUNCIL
On agenda: Final action: 11/23/2021
Effective date:    
Title: Resolution relative to the cost participation and installation of traffic signal improvements under three Congestion Mitigation Air Quality projects in various Aldermanic Districts at a total estimated cost of $3,626,155.96, with an estimated grantor share of $2,900,924.77, and an estimated City share of $725,231.19.
Sponsors: THE CHAIR
Indexes: TRAFFIC CONTROL SIGNALS
Attachments: 1. Agreement Project 298422-92, 2. Map 298422-92, 3. Cost Analysis 298422-92, 4. Agreement Project 298422-93, 5. Map 298422-93, 6. Cost Analysis 298422-93, 7. Agreement Project 298428-92, 8. Map 298428-92, 9. Cost Analysis 298428-92, 10. Resolution Cert (3 Projects)

Number

210999

Version

ORIGINAL

Reference

 

Sponsor

THE CHAIR

Title

Resolution relative to the cost participation and installation of traffic signal improvements under three Congestion Mitigation Air Quality projects in various Aldermanic Districts at a total estimated cost of $3,626,155.96, with an estimated grantor share of $2,900,924.77, and an estimated City share of $725,231.19.

Analysis

This resolution authorizes the Commissioner of Public Works and Comptroller to enter into three Local Force Account agreements with the Wisconsin Department of Transportation for the installation of traffic signal improvements using City forces at various intersections citywide under in various Aldermanic Districts at a total estimated cost of $3,626,155.96, with an estimated grantor share of $2,900,924.77, and an estimated City share of $725,231.19 and to install these improvements upon execution of the agreements. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project.

Body

Whereas, Three Project Agreements for the installation of traffic signal improvements under the Congestion Mitigation Air Quality program were approved by the Common Council under File Numbers 191663 and 200575; and

 

Whereas, The Congestion Mitigation Air Quality program is intended to reduce delay and vehicle emissions; and

 

Whereas, Two hundred two intersections have been identified for replacement of traffic signal controllers and installation of improved communications; and

 

Whereas, The total estimated cost of these projects is $3,357,551.81 for the upgrade of traffic control signals; and

 

Whereas, The total estimated cost for state review for the projects is $268,604.15; and

 

Whereas, $725,231.19 is not reimbursable and is included in the Division’s 2021 Capital Purpose Project Grant Number ST320210000; and

 

Whereas, $2,686,041.45 is reimbursable from the Wisconsin Department of Transportation, and should be earmarked for this project in the 2021 Capital Grant and Aids Projects Fund Project Grant Number SP032210100; and

 

Whereas, $214,883.32, is non-reimbursable from the Wisconsin Department of Transportation; and

 

Whereas,  The State cannot proceed with any project cost overruns or changes in scope of more than 5% without prior Department of Public Works approval; and   

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee at the next scheduled meeting of any such project cost overruns or changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100% liable for any such project cost overruns or changes in scope as approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be liable for any costs incurred by the State should the City decide to withdraw from the project; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works and the Comptroller are authorized to enter into three Local Force Account agreements with the Wisconsin Department of Transportation for the installation of traffic control signal improvements with City forces under three Congestion Mitigation Air Quality projects with unit prices based on a predetermined estimate prepared under the Federal State aided highway program, copies of which are attached to this resolution, and is incorporated into this resolution as though set forth in full; and, be it

 

Further Resolved, That upon approval of this contract, that the Commissioner of Public Works is directed to install traffic signal improvements with City forces at 202 intersections citywide; and, be it

 

Further Resolved, That upon approval of this contract, the City Comptroller is hereby authorized to create within the Capital Grant and Aid Projects Fund the appropriate Project Grant Chartfield Value for this project; and transfer to these accounts the amount required under the agreement and City accounting policy, but not to exceed a ten percent increase of the total amounts reserved for the grantor's share and local share or $5,000, whichever is greater as follows:

 

Location:

Project I.D.-2984-28-92

ATC Controller and Communications Upgrade Grant #3

79 Intersections

 

City of Milwaukee Share

Fund Number-0333

Project Grant Number-ST320210000

$292,927.53

 

Grantor Reimbursable Cash - Traffic Control

Fund Number-0306

Project Grant Number-SP032210100

$1,084,916.77

 

Grantor Non-Reimbursable-$86,793.34

 

Total-$1,464,637.64

 

Previously Authorized for Traffic Control Improvements-$0

Current Estimated Cost of the Total Project Including this Resolution-$1,891,300

Original Estimated Cost of the Total Project (Common Council Resolution File Number 191663)-$1,891,300

 

Location:

Project I.D.-2984-22-92

ATC Controller and Communications Upgrade Grant #6

53 Intersections

 

City of Milwaukee Share

Fund Number-0333

Project Grant Number-ST320210000

$175,831.31

 

Grantor Reimbursable Cash - Traffic Control

Fund Number-0306

Project Grant Number-SP032210100

$651,227.06

 

Grantor Non-Reimbursable-$52,098.17

 

Total-$879,156.54

 

Previously Authorized for Traffic Control Improvements-$0

Current Estimated Cost of the Total Project Including this Resolution-$1,423,800

Original Estimated Cost of the Total Project (Common Council Resolution File Number 200575)-$1,423,800

 

Location:

Project I.D.-2984-22-93

ATC Controller and Communications Upgrade Grant #7

70 Intersections

 

City of Milwaukee Share

Fund Number-0333

Project Grant Number-ST320210000

$256,472.35

 

Grantor Reimbursable Cash - Traffic Control

Fund Number-0306

Project Grant Number-SP032210100

$949,897.62

 

Grantor Non-Reimbursable-$75,991.81

 

Total-$1,282,361.78

 

Previously Authorized for Traffic Control Improvements-$0

Current Estimated Cost of the Total Project Including this Resolution-$2,038,500

Original Estimated Cost of the Total Project (Common Council Resolution File Number 200575)-$2,038,500

 

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

SCOTT C. REINBACHER:C. Murphy

October 13, 2021