File #: 210947    Version:
Type: Resolution Status: Passed
File created: 10/12/2021 In control: COMMON COUNCIL
On agenda: Final action: 11/2/2021
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $2,720,408 for a total estimated cost of these projects being $3,047,528.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

210947

Version

Substitute 1

Reference

201140

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $2,720,408 for a total estimated cost of these projects being $3,047,528.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $2,720,408.  The total estimated cost of these projects is $3,047,528.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

City Wide

 

Work done by Contractors/Sewer Alterations  (WT410210770)  File Number 201140:  Water Main Alterations (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 - Additional funds, $10,000).  The total estimated cost of this project including the requested amount is $15,000.  This project is anticipated to be completed during the 2021 construction season. 

 

13th Aldermanic District

 

W Grange Avenue Bridge over CP RR B-40-0500 (BR320181001/ST320181001) (2365-07-00) File Number 181112: Bridge rehabilitation and approach roadways.

Grantor Non-Reimbursable Paving Fund -- $406,796

Grantor Reimbursable Paving Fund -- $61,020

City Share Non-assessable Paving Fund -- $275,262

Grantor Non-Reimbursable Structure Fund -- $1,156,367

Grantor Reimbursable Structure Fund -- $173,455

City Share Non-assessable Structure Fund -- $637,508

 

These funds are to be transferred to the construction account BR3201810XX/ST3201810XX (2365-07-70)

Previously authorized for project construction: $0.00

Current estimated cost of total project including this resolution: $3,032,528.00

Original estimated cost of the project (Resolution 181112): $2,584,165.00

This project is anticipated to be completed during the 2022 construction season.

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Holly Rutenbeck/dl