File #: 210302    Version:
Type: Resolution Status: Passed
File created: 6/15/2021 In control: COMMON COUNCIL
On agenda: Final action: 7/7/2021
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $875,100 for a total estimated cost of $946,100.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Official Notice 14.pdf, 2. Signed letter 14.pdf, 3. Signed AD14.pdf, 4. Notice published 7/23/2021
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
7/23/20211 CITY CLERK PUBLISHED   Action details Meeting details Not available
7/15/20211 MAYOR SIGNED   Action details Meeting details Not available
7/7/20211 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
6/23/20211 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW 9th Aldermanic District W. Clinton Ave. – N. 76th St. to point west of N. 76th St. (ST211190208) Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (5’ width of tree border area), and grading. Ald. Perez moved approval. (Prevailed 5-0) N. 53rd St. – W. Cody St. to the cul-de-sac north (ST211210195) Install traffic calming speed hump(s). Ald. Borkowski moved approval. (Prevailed 5-0) 10th Aldermanic District W. Philip Pl. – N. 58th St. to N. 60th St. (ST211200124) Concrete pavement reconstruction, replace sidewalk and driveway approaches where necessary, sodding (8’ width of tree border area), and grading. Ald. Stamper moved approval. (Prevailed 5-0) 11th Aldermanic District W. Fernwood Cir. – (West) W. Honey Creek Dr. to W. Honey Creek Dr. (ST211200119) Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8’ width of tree border area), and grading. Ald. Borkowski moved approval. (Prevailed 5-0) 13th Aldermanic District W. Whitaker Ave. – S. 20th St. to S. Louisiana Ave. (ST211200125) Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8’ width of tree border area), and grading. Ald. Zamarripa moved approval. (Prevailed 5-0) 15th Aldermanic District W. Lloyd St. – N. 12th St. to N. 14th St. (ST211210182) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 5-0) W. Meinecke Ave. – N. 19th St. to N. 20th St. (ST211210183) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 5-0) W. Wright St. – N. 47th St. to N. 49th St. (ST211210184) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 5-0) N. 12th St. – W. Hadley St. to W. Locust St. (ST211210175) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 5-0) N. 40th St. – W. Hadley St. to W. Locust St. (ST211210178) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 5-0) N. 44th St. – W. Wright St. to W. Clarke St. (ST211210179) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 5-0) N. 46th St. – W. Clarke St. to W. Center St. (ST211210180) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 5-0) N. 47th St. – W. Meinecke Ave. to W. Wright St. (ST211210181) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 5-0)
Pass5:0 Action details Meeting details Video Video
6/15/20210 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

210302

Version

SUBSTITUTE 1

Reference

191262

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $875,100 for a total estimated cost of $946,100.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $875,100. The total estimated cost of these projects is $946,100.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

9th Aldermanic District

 

W. Clinton Ave. - N. 76th St. to point west of N. 76th St. (ST211190208) File Number 191262: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (5’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $45,100; Nonassessable Reconstruction Paving Fund  -- $265,000).   The total estimated cost of this project including the requested amount is $330,000. This project is anticipated to be completed during the 2021-22 construction season.

 

N. 53rd St. - W. Cody St. to the cul-de-sac north (ST211210195) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $4,000; Nonassessable Reconstruction Paving Fund  -- $3,000).   The total estimated cost of this project including the requested amount is $7,000. This project is anticipated to be completed during the 2021 construction season.

 

10th Aldermanic District

 

W. Philip Pl. - N. 58th St. to N. 60th St. (ST211200124) File Number 200124: Concrete pavement reconstruction, replace sidewalk and driveway approaches where necessary, sodding (8’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $2,000; Nonassessable Reconstruction Paving Fund  -- $160,000).   The total estimated cost of this project including the requested amount is $174,000. This project is anticipated to be completed during the 2021-22 construction season.

 

11th Aldermanic District

 

W. Fernwood Cir. - (West) W. Honey Creek Dr. to W. Honey Creek Dr.  (ST211200119) File Number 191972: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $21,200; Nonassessable Reconstruction Paving Fund  -- $160,000).   The total estimated cost of this project including the requested amount is $261,000. This project is anticipated to be completed during the 2021-22 construction season.

 

13th Aldermanic District

 

W. Whitaker Ave. - S. 20th St. to S. Louisiana Ave. (ST211200125) File Number 200228: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $11,700; Nonassessable Reconstruction Paving Fund  -- $125,000).   The total estimated cost of this project including the requested amount is $156,000. This project is anticipated to be completed during the 2021-22 construction season.

 

15th Aldermanic District

 

W. Lloyd St. - N. 12th St. to N. 14th St. (ST211210182) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $3,000; Nonassessable Reconstruction Paving Fund  -- $10,000).   The total estimated cost of this project including the requested amount is $13,000. This project is anticipated to be completed during the 2021 construction season.

 

W. Meinecke Ave. - N. 19th St. to N. 20th St. (ST211210183) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $1,800; Nonassessable Reconstruction Paving Fund  -- $6,200).   The total estimated cost of this project including the requested amount is $8,000. This project is anticipated to be completed during the 2021 construction season.

 

W. Wright St. - N. 47th St. to N. 49th St. (ST211210184) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $1,200; Nonassessable Reconstruction Paving Fund  -- $12,800).   The total estimated cost of this project including the requested amount is $14,000. This project is anticipated to be completed during the 2021 construction season.

 

 

N. 12th St. - W. Hadley St. to W. Locust St. (ST211210175) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,500; Nonassessable Reconstruction Paving Fund  -- $2,000).   The total estimated cost of this project including the requested amount is $8,500. This project is anticipated to be completed during the 2021 construction season.

 

N. 40th St. - W. Hadley St. to W. Locust St. (ST211210178) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $8,000; Nonassessable Reconstruction Paving Fund  -- $1,000).   The total estimated cost of this project including the requested amount is $9,000. This project is anticipated to be completed during the 2021 construction season.

 

N. 44th St. - W. Wright St. to W. Clarke St. (ST211210179) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $4,000; Nonassessable Reconstruction Paving Fund  -- $4,000).   The total estimated cost of this project including the requested amount is $8,000. This project is anticipated to be completed during the 2021 construction season.

 

N. 46th St. - W. Clarke St. to W. Center St. (ST211210180) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $7,800; Nonassessable Reconstruction Paving Fund  -- $1,000).   The total estimated cost of this project including the requested amount is $8,800. This project is anticipated to be completed during the 2021 construction season.

 

N. 47th St. - W. Meinecke Ave. to W. Wright St. (ST211210181) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $7,800; Nonassessable Reconstruction Paving Fund  -- $1,000).   The total estimated cost of this project including the requested amount is $8,800. This project is anticipated to be completed during the 2021 construction season.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

 

Further Resolved, That projects:   

W. Clinton Ave. (ST211190208), N. 53rd St. (ST211210195), W. Philip Pl. (ST211200124),  W. Fernwood Cir. (ST211200119),  W. Whitaker Ave. (ST211200125), W. Lloyd St. (ST211210182), W. Meinecke Ave. (ST211210183),   W. Wright St. (ST211210184), N. 12th St. (ST211210175), N. 40th St. (ST211210178), N. 44th St. (ST211210179), N. 46th St. (ST211210180),  N. 47th St. (ST211210181) will be billed after January 1, 2023, but not before 12 months after the project contract has been completed.

 

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Afr 14

06/23/2021