File #: 201250    Version: 0
Type: Resolution Status: Passed
File created: 1/19/2021 In control: COMMON COUNCIL
On agenda: Final action: 2/9/2021
Effective date:    
Title: Resolution authorizing the City Comptroller to transfer additional funds to previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the design and construction of various projects in various Aldermanic Districts a total estimated cost increase for the projects of $105,000, with one hundred percent of the increase being City funded.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. 2195-04-00.pdf, 2. 2545-03-91.pdf

Number

201250

Version

ORIGINAL

Reference

 

Sponsor

THE CHAIR

Title

Resolution authorizing the City Comptroller to transfer additional funds to previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the design and construction of various projects in various Aldermanic Districts a total estimated cost increase for the projects of $105,000, with one hundred percent of the increase being City funded.

Analysis

Resolution authorizing the City Comptroller to transfer additional funds to previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the design and construction of various projects in various Aldermanic Districts a total estimated cost increase for the projects of $105,000, with one hundred percent of the increase being City funded.

Body

Whereas, Additional design and construction work has resulted in an increased costs charged against the projects; and

 

Whereas, Additional funds are, therefore, necessary to complete the design and construction of the projects; now, therefore be it

 

Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:

 

Project Grant Value

Project ID 2545-03-91

ST320100815

West Hampton Avenue - North Green Bay Avenue to

North Teutonia Avenue

 

City Share Non-Assessable Fund, Paving

Fund 0333

$5,000

 

Total - $5,000

 

Previously authorized for traffic construction - $184,130.40

Current estimated cost of the total project including this resolution - $3,842,935.00

Original estimated cost of the total project (Resolution File Numbers 100021 and 111697) -$3,842,935.00

 

Project Grant Value

Project ID 2195-04-00

ST320191101

East Wells Street - North Broadway to North Prospect Avenue

 

City Share Non-Assessable Fund, Paving

ST20210000

Fund 0333

$100,000

 

Previously authorized for design - ​$660,000

Current estimated cost of the total project including this resolution - $5,835,000

Original estimated cost of the total project (Resolution File Numbers 191112) - $5,675,000

 

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

DAVID J. TAPIA:C. Murphy

January 8, 2021