Number
200227
Version
SUBSTITUTE 2
Reference
090969
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $359,600 for a total estimated cost of $372,600.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $359,600. The total estimated cost of these projects is $372,600.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
1st Aldermanic District
N. Hopkins St. - W. Sheridan Ave. to W. Silver Spring Dr. (ST211180291) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $5,100; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $7,100. This project is anticipated to be completed during the 2020 construction season.
W. Purdue St. - N. 19th Pl. to N. 20th St. (ST211190186) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $2,800; Nonassessable Reconstruction Paving Fund -- $4,500). The total estimated cost of this project including the requested amount is $7,300. This project is anticipated to be completed during the 2020 construction season.
W. Thurston Ave. - N. 32nd St. to N. 33rd St. (ST211190188) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $1,900; Nonassessable Reconstruction Paving Fund -- $5,400). The total estimated cost of this project including the requested amount is $7,300. This project is anticipated to be completed during the 2020 construction season.
N. 13th St. - W. Capitol Dr. to W. Fiebrantz Ave. (ST211190190) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,600; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $8,600. This project is anticipated to be completed during the 2020 construction season.
N. 19th Pl. - W. Courtland Ave. to W. Hampton Ave. (ST211190175) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,800; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $8,800. This project is anticipated to be completed during the 2020 construction season.
2nd Aldermanic District
N. 72nd St. - W. Courtland Ave. to W. Hampton Ave. (ST211200106) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,400; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $8,400. This project is anticipated to be completed during the 2020 construction season.
N. 72nd St. - W. Hampton Ave. to W. Stark St. (ST211180245) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,500; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $8,500. This project is anticipated to be completed during the 2020 construction season.
N. 73rd St. - W. Marion St. to W. Congress St. (ST211180244) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,700; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $8,700. This project is anticipated to be completed during the 2020 construction season.
3rd Aldermanic District
Alley between N. Bremen St., E. Center St., N. Fratney St., E. Hadley St. (ST212080107) File Number 090969: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $40,500; Nonassessable Alley Paving Fund -- $75,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2020 construction season
7th Aldermanic District
W. Leon Tr. - W. Hoyt Pl. to N. 48th St. (ST211190185) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,100; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $8,100. This project is anticipated to be completed during the 2020 construction season.
N. 45th St. - W. Congress St. to W. Glendale Ave. (ST211190180) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $14,000; Nonassessable Reconstruction Paving Fund -- $4,000). The total estimated cost of this project including the requested amount is $18,000. This project is anticipated to be completed during the 2020 construction season.
N. 49th St. - W. Marion St. to W. Congress St. (ST211200115) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $8,200; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $10,200. This project is anticipated to be completed during the 2020 construction season.
10th Aldermanic District
Alley between W. Garfield Ave., W. North Ave., N. 51st St., N. 52nd St. (ST212170104) File Number 150614: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $51,500; Nonassessable Alley Paving Fund -- $70,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2020 construction season
15th Aldermanic District
N. 9th St. - W. Hadley St. to W. Locust St. (ST211190202) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,600; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $8,600. This project is anticipated to be completed during the 2020 construction season.
N. 15th St. - W. Lloyd St. to W. North Ave. (ST211110153) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $11,000; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $13,000. This project is anticipated to be completed during the 2020 construction season.
; and
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
Further Resolved, That projects N. Hopkins St. (ST211180291); W. Purdue St. (ST211190186); W. Thurston Ave (ST211190188); N. 13th St. (ST211190190); N. 19th Pl. (ST211190175); N. 72nd St. (ST211200106); N. 72nd St. (ST211180245); N. 73rd St. (ST211180244); Alley N. Bremen St. (ST212080107); W. Leon Tr. (ST211190185); N. 45th St. (ST211190180); N. 49th St. ST211200115); Alley W. Garfield Ave. (ST212170104); N. 9th St. (ST211190202); N. 15th St. (ST211110153) will be billed after January 1, 2022, but not before 12 months after the project contract has been completed.
Requestor
Infrastructure Services Division
Drafter
Mary Dziewiontkoski/dl
Afr 13 Sub
07/07/2020