Resolution authorizing the City Comptroller to transfer additional funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the design and construction of various projects in various Aldermanic districts with a total estimated cost increase for the projects of $272,254.03, with an estimated Grantor share of $13,254.03, and an estimated City share of $259,000.
Analysis
Resolution authorizing the City Comptroller to transfer additional funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the design and construction of various projects in various Aldermanic districts with a total estimated cost increase for the projects of $272,254.03, with an estimated Grantor share of $13,254.03, and an estimated City share of $259,000.
Body
Whereas, Additional design and construction work has resulted in an increased costs charged against various capital improvement projects; and
Whereas, Additional funds are, therefore, necessary to complete the design and construction of the projects; now, therefore be it
Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:
Project Grant Value
Project ID 2505-00-95
ST320120615
South 13th Street
West Forest Home Avenue to Windlake Avenue
Grantor Reimbursable
Fund Number - 0306
Project Grant Number - SP032200100
$13,254.03
Total - $13,254.03
Previously authorized for traffic construction - $173,464.12
Current estimated cost of the total project including this resolution - $2,611,395.15
Original estimated cost of the total project (Resolution File Number 111507) - $1,797,300
Project Grant Value
Project ID 2984-08-95
ST320120515
Install Monotube Mast Arms 10 Local Intersections
City of Milwaukee Share
Fund Number - 0333
Project Grant Number - ST320200000
$20,000
Total - $20,000
Previously authorized for traffic construction - $319,194.39
Current estimated cost of the total project including this resolution - $1,316,789.32
Original estimated cost of the total project (Resolution File Number 111478) - $1,214,000
Project Grant Value
Project ID 2984-14-02
ST320161201
North Fratney / East Wright Bike Boulevards
Milwaukee County
Preliminary Engineering
City of Milwaukee Share
Fund Number - 0333
Project Grant Number-ST320200000
$14,000
Total - $14,000
Previously Authorized for Preliminary Engineering-$133,954
Current Estimated Cost of the Total Project Including this Resolution- $836,114
Original estimated cost of the project: (Resolution 160794): $810,860
Project Grant Value
Project Grant Value
Project ID 2595-03-73
ST320160710
North 60th Street from West Capitol Drive to Hampton Avenue
City Share Non-Assessable Fund, Paving
Fund 0333
Project Grant Number ST320200000
$225,000
Total - $225,000
Previously authorized for construction - $9,248,116.29
Current estimated cost of the total project including this resolution - $10,510,616.29
Original estimated cost of the total project (Resolution File Number 151714) - $8,650,500
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
J. BLAKEMAN/C. Murphy
April 3, 2020