powered help
header-left header-center header-right
File #: 191887    Version:
Type: Resolution Status: Passed
File created: 3/24/2020 In control: COMMON COUNCIL
On agenda: Final action: 4/14/2020
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,228,000 for a total estimated cost of these projects being $6,198,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

 

Number

191887

Version

SUBSTITUTE 1

Reference

190743

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,228,000 for a total estimated cost of these projects being $6,198,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $4,228,000.  The total estimated cost of these projects is $6,198,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

2nd Aldermanic District

 

W. Bobolink Ave. - N. 68th St. to N. 70th St. (WT410200637) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $175,000).   The total estimated cost of this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2020 construction season. 

 

W. Stark St. - N. 64th St to N. 67th St. (WT410200646) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $305,000).   The total estimated cost of this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 67th St. - W. Fond du Lac Av. to W. Stark St. (WT410200647) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $220,000).   The total estimated cost of this project including the requested amount is $235,000.  This project is anticipated to be completed during the 2020 construction season. 

 

 

4th Aldermanic District

 

E. Mason St. - N. Broadway to N. Milwaukee St. (SM495190030) File Number 190743: Relaying combined sewer.( Nonassessable Sewer Maintenance Relay Fund -- $131,000).   The total estimated cost of this project including the requested amount is $143,000.  This project is anticipated to be completed during the 2020 construction season.

 

5th Aldermanic District

 

W. Hampton Ave. - N. 92nd St. to N. Lovers Land Rd. (SM499190016) File Number 190518: Traffic Island Bioswales.  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $415,000).   The total estimated cost of this project including the requested amount is $435,000.  This project is anticipated to be completed during the 2020 construction season. 

 

6th Aldermanic District

 

W. Nash St. - N. 14th St. to N. 15th St. (SM495190050) File Number 190870: Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $93,000).   The total estimated cost of this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2020 construction season

 

N. 6th St. - W. Hadley St. to 400’ north of W. Hadley St. (SM495180029)  File Number 180160: Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $122,000).   The total estimated cost of this project including the requested amount is $134,000.  This project is anticipated to be completed during the 2020 construction season.

 

N. 14th St. - W. Hadley St. to W. Chambers St. (SM495190057)  File Number 191008:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $260,000).   The total estimated cost of this project including the requested amount is $272,000.  This project is anticipated to be completed during the 2020 construction season. 

 

7th Aldermanic District

 

N. 48th St. - W. Parkway Dr. to W. Glendale Av.  (WT410200651) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $245,000).   The total estimated cost of this project including the requested amount is $260,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 53rd St. - W. Glendale Av. to W. Hampton Av.  (WT410200652) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $370,000).   The total estimated cost of this project including the requested amount is $395,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 56th St. - W. Parkway Dr. to W. Hampton Av.  (WT410200653) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $350,000).   The total estimated cost of this project including the requested amount is $375,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 57th St.-  W. Parkway Dr. to W Hampton Av. (WT410200654) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $285,000).   The total estimated cost of this project including the requested amount is $305,000.  This project is anticipated to be completed during the 2020 construction season. 

 

 

10th and 15th Aldermanic Districts

 

W. Meinecke Ave. - N. 51st St. to 100’ west of N. 51st St. (SM495190044)  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $64,000). The total estimated cost of this project including the requested amount is $74,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 51st St. - W. Garfield Ave. to W. Meinecke Ave.  (SM495190048)  File Number 190870:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $335,000).   The total estimated cost of this project including the requested amount is $350,000.  This project is anticipated to be completed during the 2020 construction season. 

 

11th Aldermanic District

 

S. 63rd - W. Burdick Ave. to W. Morgan Ave. (WT410200676) File Number 190037: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $450,000).   The total estimated cost of this project including the requested amount is $480,000.  This project is anticipated to be completed during the 2020 construction season. 

 

15th Aldermanic District

 

N. 19th St. - W. Wright St. to W. Clarke St. (SM495190054) File Number 190870: Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $208,000).   The total estimated cost of this project including the requested amount is $220,000.  This project is anticipated to be completed during the 2020 construction season. 

 

City wide

 

Handicap Ramp work to meet ADA requirements for 2020 High Impact Projects (ST216200102):  (Nonassessable High Impact Streets -- $200,000, additional funds).  The total estimated cost for this project including the requested amount is $1,900,000.  This project is anticipated to be completed during the 2020 construction season

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Nfr 10 sub

03/27/2020