Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $6,759,000 for a total estimated cost of these projects being $9,968,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
191556
Version
SUBSTITUTE 1
Reference
191263
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $6,759,000 for a total estimated cost of these projects being $9,968,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $6,759,000. The total estimated cost of these projects is $9,968,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

2nd Aldermanic District

N. 69th St. - W. Marion St. to W. Glendale Ave. (WT410200663) File Number 191263: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0; (Nonassessable Water Fund Budget Line 6410 -- $565,000). The total estimated cost of this project including the requested amount is $600,000. This project is anticipated to be completed during the 2020 construction season.

3rd Aldermanic District

1720 N. Arlington Pl. (SM499180110) File Numbers 180030 and 190519:
1720 N. Arlington Permeable Paver Project
Stormwater Quality (Non Assessable Water Quality Projects to meet TMDL Requirements, $55,000 additional funds). The total estimated cost for this project including the requested amount is $220,000. The project is anticipated to be completed in 2020.

4th Aldermanic District

N. 32nd St.-W. Mt. Vernon Ave. to W. St. Paul Ave. (SM495190010) File Number 181588: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $122,000). The total estimat...