File #: 191264    Version:
Type: Resolution Status: Passed
File created: 11/26/2019 In control: COMMON COUNCIL
On agenda: Final action: 12/17/2019
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $16,528,160 for a total estimated cost of these projects being $17,919,114.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
191264
Version
SUBSTITUTE 1
Reference
191263
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $16,528,160 for a total estimated cost of these projects being $17,919,114.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $16,528,160. The total estimated cost of these projects is $17,919,114.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

3rd and 6th Aldermanic Districts

N. Fratney St. - E. Meinecke Ave. to E. Keefe Ave. and E. Wright St. - N. Palmer St. to the Oak Leaf Trail. (ST320161201) (2984-14-02) File Number 160794: Construct two bicycle boulevards.

Grantor Non-Reimbursable Paving Fund -- $28,000
Grantor Reimbursable Paving Fund -- $522,528
City Share Non-assessable Paving Fund -- $137,632

These funds are to be transferred to the construction account (ST3201612XX)
(2984-14-72)

Previously authorized for project construction: $0.00
Current estimated cost of total project including this resolution: $822,114
Original estimated cost of the project: (Resolution 160794): $810,860

This project is anticipated to be completed during the 2020 construction season.

5th Aldermanic District

W. Appleton Pl. -- W. Appleton Ave. to N. 115th St. (SM492190010) File Number 191263: Developer Sewer Projects. Installing new sanitary sewer. (Developer Sewer Fund -- $1,180,000). The total estimated cost of this project includ...