File #: 191149    Version:
Type: Resolution Status: Passed
File created: 11/5/2019 In control: COMMON COUNCIL
On agenda: Final action: 11/26/2019
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $63,000 for a total estimated cost of $63,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Official Notice 4, 2. Signed Ad 4.pdf, 3. Signed letter.pdf, 4. Proof of Publication
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
12/4/20191 MAYOR SIGNED   Action details Meeting details Not available
11/26/20191 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
11/13/20191 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW David Tapia - DPW Mike Amsden - DPW 2nd and 7th Aldermanic Districts N. 60th St. -- W. Capitol Dr. to W. Hampton Av. (ST320160701). Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches as necessary, sodding (7 foot wide tree border), and grading. Ald. Johnson moved to hold to the call of the chair. (Prevailed 5-0) 4th Aldermanic District W. St. Paul Ave. – N. 29th St. to N. 30th St. (ST211190160). Install traffic calming speed hump(s). Ald. Kovac moved approval. (Prevailed 5-0) 6th Aldermanic District N. Booth St. -- W. Hadley St. to W. Locust St. (ST211190159). Install traffic calming speed hump(s). Ald. Johnson moved approval. (Prevailed 5-0) 7th Aldermanic District N. 40th St. -- W. Chambers St. to W. Burleigh St. (ST211180284). Install traffic calming speed hump(s). Linda Pullin-Algee 3008 N 40th St stated the neighborhood is deteriorating and everyone is at the mercy of careless drivers. Ald. Johnson moved approval. (Prevailed 5-0) N. 42nd St. – W. Roosevelt Dr. to W. Capitol Dr. (ST211180286). Install traffic calming speed hump(s). Ald. Kovac moved approval. (Prevailed 5-0) N. 58th St. - W. Hampton Av. to W. Fairmount Av. (ST211180289). Install traffic calming speed hump(s). Ald. Murphy moved approval. (Prevailed 5-0) Ald. Kovac moved approval as amended. (Prevailed 5-0)
Pass5:0 Action details Meeting details Video Video
11/5/20190 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
191149
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $63,000 for a total estimated cost of $63,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $63,000. The total estimated cost of these projects is $63,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

4th Aldermanic District

W. St. Paul Ave. - N. 29th St. to N. 30th St. (ST211190160). Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $3,000; Nonassessable Reconstruction Paving Fund -- $5,400). The total estimated cost for this project including the requested amount is $8,400. This project is anticipated to be completed during the 2020 construction season.

6th Aldermanic District

N. Booth St. -- W. Hadley St. to W. Locust St. (ST211190159). Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $7,400; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost for this project including the requested amount is $9,400. This project is anticipated to be completed during the 2020 construction season.

7th Aldermanic District

N. 40th St. -- W. Chambers St. to W. Burleigh St. (ST211180284). Install traffic calming speed hump(s). (Assessable Rec...

Click here for full text