Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,376,000 for a total estimated cost of these projects being $4,066,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

191009

Version

SUBSTITUTE 1

Reference

150118

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,376,000 for a total estimated cost of these projects being $4,066,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $3,376,000.  The total estimated cost of these projects is $4,066,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

1st Aldermanic District

 

W. Olive St. - N. 22nd St. to W. Roosevelt Dr.  (WT410160691)  File Number 150118:  Water Main Relay and Lead Service Replacement.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $455,000).   The total estimated cost of this project including the requested amount is $475,000.  This project is anticipated to be completed during the 2020 construction season. 

 

2nd and 7th Aldermanic Districts

 

N. 60th St. - W. Capitol Dr. to W. Hampton Ave.  (WT410200003) File Number 181686: Hydrant Alteration.  (Nonassessable Water Fund Budget Line 5010 -- $0; (Nonassessable Water Fund Budget Line 6410 -- $45,000).   The total estimated cost of this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2020 construction season. 

 

3rd Aldermanic District

 

E. Belleview Pl. - N. Downer Ave. to N. Lake Dr.  (WT410160688)  File Number 151289:  Water Main Relay and Lead Service Replacement.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $35,000 - Additional Funds).   The total estimated cost of this project including the requested amount is $350,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. Summit Ave. - E. Belleview Pl. to N. Downer Ave. (WT410160689)  File Number 151289:  Water Main Relay and Lead Service Replacement.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $30,000 - Additional Funds).   The total estimated cost of this project including the requested amount is $285,000.  This project is anticipated to be completed during the 2020 construction season. 

 

7th Aldermanic District

 

W. Melvina Pl. - N. 30th St. to N. Hopkins St. (WT410160606)  File Number 141514:  Water Main Relay.  (Nonassessable Water Fund Budget Line 5010 -- $0; (Nonassessable Water Fund Budget Line 6410 -- $45,000).   The total estimated cost of this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2020 construction season. 

 

15th Aldermanic District

 

W. Medford Ave. - N. 26th St. to N. 27th St. (SM495180101) File Number 181383: Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $969,000).   The total estimated cost of this project including the requested amount is $989,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 16th St. - W. Hadley St. to W. Locust St. (WT410160634)  File Number 150118:  Water Main Relay and Lead Service Replacement.  (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $412,000).   The total estimated cost of this project including the requested amount is $430,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 27th St. - W. Medford Ave. to W. Center St. (SM495180100) File Number 181383:  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $

1,362,000.   The total estimated cost of this project including the requested amount is $1,382,000.  This project is anticipated to be completed during the 2020 construction season. 

 

Greenfield

 

S. 108th St.@ W. Layton Ave. - (WT410190008)  File Number 190285:  Hydrant Alteration.  (Nonassessable Water Fund Budget Line 5010 -- $0; (Nonassessable Water Fund Budget Line 6410 -- $20,000).   The total estimated cost of this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2020 construction season. 

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 