Title: Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,046,000 for a total estimated cost of these projects being $3,321,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

190744

Version

SUBSTITUTE 1

Reference

171854

Sponsor

THE CHAIR

Title

Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,046,000 for a total estimated cost of these projects being $3,321,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $3,046,000.  The total estimated cost of these projects is $3,321,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

1st Aldermanic District

 

N. 11th St. - W. Birch Ave. to W. Silver Spring Dr. (WT410190674) File Number 171854:  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $133,000).   The total estimated cost of this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2020 construction season. 

 

5th Aldermanic District

 

W. Jeffrey Ct. - N. 110th St. to 250’ west of N. 110th St. (WT410190604)  File Number 171854: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 - 129,000).  The total estimated cost of this project including the requested amount is $145,000.  This project is anticipated to be completed during the 2020 construction season. 

 

W. Jeffrey Ln. -- N. 108th to N. 110th St.   (WT410190601)  File Number 171854: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $317,000). The total estimated cost of this project including the requested amount is $340,000.  This project is anticipated to be completed during the 2020 construction season. 

 

W. Nash St. - N. 96th St. to N. 100th St.  (WT410190610)  File Number 171854:  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $5,000;

Nonassessable Water Fund Budget Line 6410 -- $440,000).

 The total estimated cost of this project including the requested amount is $470,000.  This project is anticipated to be completed during the 2020 construction season. 

 

W. Stark St. - N. 107th St. to N. 110th St.   (WT410190602) File Number 171854:  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $332,000).  The total estimated cost of this project including the requested amount is $360,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 97th St. - W. Nash St. to W. Metcalf Pl.  (WT410190607)  File Number 171584:  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $228,000). The total estimated cost of this project including the requested amount is $245,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 97th Pl.-W. Nash St. to W. Metcalf Pl.  (WT410190608)  File Number 171854: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $257,000).  The total estimated cost of this project including the requested amount is $280,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 108th St. - W. Jeffrey Ln. to W. Villard Ave. (WT410190603)  File Number 171854: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $6,000; Nonassessable Water Fund Budget Line 6410 -- $604,000). The total estimated cost of this project including the requested amount is $645,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 110th St. - W. Hampton Ave. to W. Cameron Ave. (WT410190605)  File Number 171854: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $237,000). The total estimated cost of this project including the requested amount is $260,000.  This project is anticipated to be completed during the 2020 construction season. 

 

7th Aldermanic District

 

N. 47th St. - W. Capitol Dr. to W. Fiebrantz Ave. (WT410190654)  File Number 171854:  Relaying water main and lead lateral replacement (ROS).  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $213,000).   The total estimated cost of this project including the requested amount is $230,000.  This project is anticipated to be completed during the 2020 construction season. 

 

12th Aldermanic District

 

Windlake Avenue Bioswale Project  -- S. 19th St. at W. Windlake Ave.   (SM499160114)  File Numbers 160590, 160589 and 151848: (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000, additional funds).  The total estimated cost of this project including the requested amount is $56,000.  This project is anticipated to be completed during the 2019 construction season. 

 

City Wide

 

Permanent Pavement Replacement --  (SM495180093)  File Number 181227:  Sewer Maintenance Relay.  (Nonassessable Sewer Structure Pavement Replacement - $125,000.   The total estimated cost of this project including the requested amount is $140,000.  This project is anticipated to be completed during the 2019 construction season. 

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Nfr 1-- Sub

08/20/2019