Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $7,713,000 for a total estimated cost of these projects being $9,364,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $7,713,000. The total estimated cost of these projects is $9,364,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
2nd Aldermanic District
N. 66th St. - W. Custer Ave. to W. Silver Spring Dr. (SM495190024) File Number 190518: Installing new sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $114,000). The total estimated cost of this project including the requested amount is $126,000. This project is anticipated to be completed during the 2019 construction season.
3rd Aldermanic District
1720 N. Arlington Permeable Paver Project
1720 N. Arlington Pl. (SM499180110) File Number 180030: (Nonassessable Storm Water Quality Fund -- $160,000). The total estimated cost of this project including the requested amount is $165,000. This project is anticipated to be completed during the 2019 construction season.
2705 N. Downer Permeable Paver Project
2705 N. Downer Ave. (SM499180111) File Number 180030: (Nonassessable Storm Water Quality Fund -- $165,000). The total estimated cost of this project including the requested amount is $170,000. This project is anticipated to be completed during the 2019...