powered help
header-left header-center header-right
File #: 190518    Version:
Type: Resolution Status: Passed
File created: 7/9/2019 In control: COMMON COUNCIL
On agenda: Final action: 7/30/2019
Effective date:    
Title: Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $152,000 for a total estimated cost of these projects being $2,076,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
190518
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $152,000 for a total estimated cost of these projects being $2,076,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $152,000 with the total cost estimated to be $2,076,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st and 9th Aldermanic Districts

N. Sherman Blvd. - W. Custer Ave. to N. Hopkins St. (SM499190014) Traffic Island Bioswales. (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $20,000). The total estimated cost of this project including the requested amount is $300,000. This project is anticipated to be completed during the 2020 construction season.

2nd Aldermanic District

N. 66th St. - W. Custer Ave. to W. Silver Spring Dr. (SM495190024) Installing new sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $126,000. This project is anticipated to be completed during the 2019 construction season.

4th Aldermanic District

W. St. Paul Ave. - 190’ east of N. Vel R. Phillips Ave. to N. Vel R. Phillips Ave. (WT410190503) Relaying water main. Water main alteration. Branch Alteration. (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $22,000). The total estimated cost of this project including ...

Click here for full text